24007 W ARCHWOOD ST 91307

Certificate Information: 24007 W ARCHWOOD ST 91307

Application / Permit
21047-20000-02544
Plan Check / Job No.
B21VN16040
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 32'-0" x 15'-0" POOL WITH 6'-0" x 6'-0" SPA PER LA CITY STANDARD PLAN# 268.
Permit Issued
Issued on 1/26/2022
Issuing Office
Current Status
CofO Issued on 7/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 11/23/2021 SARKIS HARABEDIAN
Corrections Issued 11/23/2021 SARKIS HARABEDIAN
Plan Check Approved 1/26/2022 SARKIS HARABEDIAN
Issued 1/26/2022 APPLICANT
Building Plans Picked Up 1/31/2022 APPLICANT
CofO in Progress 6/29/2022 TROY SANDERS
Permit Finaled 7/7/2022 JOHN JANSON
CofO Issued 7/7/2022 JOHN JANSON
Permit Finaled 7/7/2022 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 1/14/2022 WALTER RAMIREZ

Contact Information

Contractor Way To Go Builders; Lic. No.: 1043721-B 6700 FALLBROOK AVE STE 133      WEST HILLS, CA 91307
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/8/2022 Approved TROY SANDERS
Gas Piping or Gas Test 3/8/2022 Approved TROY SANDERS
Grounding or Bonding 3/8/2022 Partial Approval TROY SANDERS
Rough-Plumbing 3/8/2022 Approved TROY SANDERS
Grounding or Bonding 3/11/2022 Partial Approval TROY SANDERS
PLUMBING-Final 3/11/2022 Not Ready for Inspection TROY SANDERS
Deputy Shotcrete 3/15/2022 Partial Approval TROY SANDERS
Grounding or Bonding 4/20/2022 Approved TROY SANDERS
Enclosure/Fence 5/23/2022 Approved TROY SANDERS
Final 6/15/2022 Corrections Issued TROY SANDERS
Pre-Gunite 6/15/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved TROY SANDERS
Final 6/29/2022 OK to Issue CofO TROY SANDERS
Pool Equipment Noise Test 7/5/2022 Approved ALFREDO FLORES