5003 N MAMMOTH AVE 91423

Certificate Information: 5003 N MAMMOTH AVE 91423

Application / Permit
21047-20000-02514
Plan Check / Job No.
B21VN15812
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 17' X 32' SWIMMING POOL WITH ATTACHED 7' X 6' SPA PER LA CITY STANDARD PLAN #242
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2021 APPLICANT
Assigned to Plan Check Engineer 11/17/2021 GURUNATH NESARAJAH
Corrections Issued 11/17/2021 GURUNATH NESARAJAH
Plan Check Approved 2/19/2022 GURUNATH NESARAJAH
Building Plans Picked Up 2/22/2022 APPLICANT
Issued 4/5/2022 APPLICANT
CofO in Progress 1/20/2023 MISAEL ESPARZA
Permit Finaled 1/21/2023 MICHAEL SMITH
CofO Issued 1/21/2023 MICHAEL SMITH
Permit Finaled 1/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 2/10/2022 WALTER RAMIREZ
Construction within easement Cleared 2/10/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Shniderman,, Jason Bernard; Lic. No.: C20524 16000 SHERMAN WAY #234      VAN NUYS, CA 91607

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 5/25/2022 Approved MISAEL ESPARZA
Pre-Gunite 5/25/2022 Corrections Issued MISAEL ESPARZA
Rough-Electrical 5/25/2022 Partial Approval MISAEL ESPARZA
Rough-Electrical 6/1/2022 Approved MISAEL ESPARZA
Deputy Shotcrete 6/2/2022 Conditional Approval MISAEL ESPARZA
Grounding or Bonding 9/13/2022 Approved MISAEL ESPARZA
Enclosure/Fence 11/7/2022 Corrections Issued MISAEL ESPARZA
Enclosure/Fence 11/18/2022 Approved MISAEL ESPARZA
Pool Equipment Noise Test 12/16/2022 Approved FELIPE PENICHE
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Not Ready MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 1/5/2023 Approved JENNIFER RABUCHIN
Final 1/5/2023 Corrections Issued JENNIFER RABUCHIN
Pre-Gunite 1/5/2023 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/5/2023 SGSOV Not Ready JENNIFER RABUCHIN
Final 1/19/2023 OK to Issue CofO MISAEL ESPARZA
Pre-Gunite 1/19/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Approved MISAEL ESPARZA