4351 N TALOFA AVE 91602

Certificate Information: 4351 N TALOFA AVE 91602

Application / Permit
21047-20000-02491
Plan Check / Job No.
B21VN15650
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14' X 22' SWIMMING POOL AND 14' X 8' SPA PER STANDARD PLAN #265
Permit Issued
Issued on 12/30/2021
Issuing Office
Current Status
CofO Issued on 8/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/15/2021 ANGELICA DAVE
Corrections Issued 11/15/2021 ANGELICA DAVE
Plan Check Approved 12/30/2021 ANGELICA MARTINEZ
Issued 12/30/2021 APPLICANT
Building Plans Picked Up 1/3/2022 APPLICANT
CofO in Progress 8/12/2022 THOMAS FINNILA
CofO in Progress 8/12/2022 THOMAS FINNILA
Permit Finaled 8/16/2022 DANIEL ORRANTE
CofO Issued 8/16/2022 DANIEL ORRANTE
Permit Finaled 8/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/7/2022 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/31/2022 Not Ready for Inspection THOMAS FINNILA
Pool Piping 3/31/2022 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 4/13/2022 Approved MATT KELLERMAN
Pre-Gunite 4/13/2022 Approved MATT KELLERMAN
Deputy Shotcrete 4/18/2022 Conditional Approval THOMAS FINNILA
Gas Piping or Gas Test 4/26/2022 Approved CHRISTOPHER DELLEFIELD
Pool Piping 4/26/2022 Approved CHRISTOPHER DELLEFIELD
Rough-Plumbing 4/26/2022 Approved CHRISTOPHER DELLEFIELD
Grounding or Bonding 5/23/2022 Corrections Issued THOMAS FINNILA
Grounding or Bonding 5/27/2022 Partial Approval THOMAS FINNILA
Enclosure/Fence 6/24/2022 Corrections Issued THOMAS FINNILA
Enclosure/Fence 7/5/2022 Approved THOMAS FINNILA
Pool Equipment Noise Test 7/13/2022 Approved FELIPE PENICHE
Final 7/19/2022 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Not Ready THOMAS FINNILA
Final 8/10/2022 OK to Issue CofO THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Approved THOMAS FINNILA