1320 S GLENAVON AVE 90291
Certificate Information: 1320 S GLENAVON AVE 90291
- Application / Permit
- 21047-20000-02471
- Plan Check / Job No.
- B21VN15443
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 31' X 19' POOL AND 10' X 8' SPA, PER LA CITY STD PLAN No. 268
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 9/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/9/2021 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/10/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 9/19/2022 | DAVID FEILER |
| Permit Finaled | 9/28/2022 | DANIEL ORRANTE |
| CofO Issued | 9/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/9/2021 | LUISANGEL VALENZUELA |
| Construction near power lines | Cleared | 3/1/2022 | TINA MIRANDA |
Contact Information
| Contractor | Keystone Remodeling Inc; Lic. No.: 1065368-B | 22120 CLARENDON ST #205 WOODLAND HILLS, CA 91367 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/9/2022 | Corrections Issued | DAVID FEILER |
| Rough-Electrical | 5/9/2022 | Not Ready for Inspection | DAVID FEILER |
| Rough-Plumbing | 5/9/2022 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 5/11/2022 | No Access for Inspection | DAVID FEILER |
| Pool Piping | 5/11/2022 | No Access for Inspection | DAVID FEILER |
| Pre-Gunite | 5/11/2022 | No Access for Inspection | DAVID FEILER |
| Rough-Electrical | 5/11/2022 | No Access for Inspection | DAVID FEILER |
| Rough-Plumbing | 5/11/2022 | No Access for Inspection | DAVID FEILER |
| Pre-Gunite | 5/13/2022 | Corrections Issued | DAVID FEILER |
| Pre-Gunite | 5/18/2022 | Approved | JESUS RODRIGUEZ |
| Deck | 5/26/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Gunite | 5/26/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Grounding or Bonding | 5/31/2022 | Approved | JESUS RODRIGUEZ |
| Enclosure/Fence | 8/12/2022 | Corrections Issued | DAVID FEILER |
| Enclosure/Fence | 8/26/2022 | Approved | DAVID FEILER |
| Equipment Noise Level | 9/6/2022 | Not Ready for Inspection | JAMES VORHIS |
| Pool Equipment Noise Test | 9/8/2022 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Approved | DAVID FEILER |
| Final | 9/12/2022 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Not Ready | DAVID FEILER |
| Final | 9/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/19/2022 | Approved | DAVID FEILER |
| Final | 9/19/2022 | OK to Issue CofO | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Approved | DAVID FEILER |