3528 S BARRINGTON AVE 90066

Certificate Information: 3528 S BARRINGTON AVE 90066

Application / Permit
21047-20000-02398
Plan Check / Job No.
B21VN14981
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16'-4" X 28'-2" POOL W/ 7' X 7' SPA WITHIN POOL SHELL AND POOL COVER PER LA CITY STANDARD PLAN #: 268 AND DETAIL #: 672
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2021 APPLICANT
Assigned to Plan Check Engineer 11/2/2021 JENNIFER LEE
Corrections Issued 11/2/2021 JENNIFER LEE
Plan Check Approved 3/1/2022 JENNIFER LEE
Issued 3/2/2022 APPLICANT
Building Plans Picked Up 3/4/2022 APPLICANT
CofO in Progress 2/16/2023 KENNETH NAGLE
Permit Finaled 2/16/2023 DANIEL ORRANTE
CofO Issued 2/16/2023 DANIEL ORRANTE
Permit Finaled 2/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/2/2021 JENNIFER LEE
Construction near power lines Cleared 2/15/2022 RIDWAN HARDY

Contact Information

Contractor Brite Pool Plastering; Lic. No.: 976733-C53 13413 CORCORAN STREET      SAN FERNANDO, CA 91340
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 4/6/2022 Corrections Issued JOHNNY MIRANDA
Pre-Gunite 5/19/2022 Corrections Issued EVAN COOPER
Pre-Gunite 5/25/2022 Approved JOHNNY MIRANDA
Deputy Shotcrete 6/3/2022 Conditional Approval JOHNNY MIRANDA
Grounding or Bonding 6/21/2022 Approved JOHNNY MIRANDA
Enclosure/Fence 7/14/2022 Approved JOHNNY MIRANDA
Pool Equipment Noise Test 8/15/2022 Approved AGUSTIN ALVAREZMORALES
Excavation/Setback/Form/Re-Bar 9/23/2022 Approved JOHNNY MIRANDA
Final 9/23/2022 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved JOHNNY MIRANDA
Final 10/21/2022 Conditional Approval JOHNNY MIRANDA