4464 N MATILIJA AVE 91423

Certificate Information: 4464 N MATILIJA AVE 91423

Application / Permit
21047-20000-02334
Plan Check / Job No.
B21VN14459
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 33'X 23' POOL AND 9' X 9' SPA PER STD PLAN #268.
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
CofO Issued on 6/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2021 APPLICANT
Assigned to Plan Check Engineer 10/22/2021 PINANK PATEL
Corrections Issued 10/22/2021 PINANK PATEL
Applicant returned to address corrections 12/17/2021 PINANK PATEL
Plan Check Approved 1/11/2022 PINANK PATEL
Issued 1/13/2022 APPLICANT
Building Plans Picked Up 1/20/2022 APPLICANT
CofO in Progress 6/8/2023 ROBERT GOLD
CofO in Progress 6/8/2023 ROBERT GOLD
CofO in Progress 6/13/2023 ROBERT GOLD
Permit Finaled 6/15/2023 MICHAEL SMITH
CofO Issued 6/15/2023 MICHAEL SMITH
Permit Finaled 6/15/2023 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Stepanyan Design; Lic. No.: 970988-B 8010 NORTH HOLLYWOOD WAY      SUN VALLEY, CA 91352
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/3/2022 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/4/2022 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 2/4/2022 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/15/2022 Approved MISAEL ESPARZA
Grounding or Bonding 2/15/2022 Partial Approval MISAEL ESPARZA
Pre-Gunite 2/15/2022 Approved MISAEL ESPARZA
Rough-Electrical 2/15/2022 Partial Approval MISAEL ESPARZA
Rough-Plumbing 2/15/2022 Partial Approval MISAEL ESPARZA
Deputy Shotcrete 2/16/2022 Conditional Approval MISAEL ESPARZA
Rough-Electrical 8/23/2022 Approved MISAEL ESPARZA
Rough-Plumbing 8/23/2022 Approved MISAEL ESPARZA
Enclosure/Fence 4/25/2023 Corrections Issued MISAEL ESPARZA
Final 4/25/2023 Not Ready for Inspection MISAEL ESPARZA
Enclosure/Fence 4/28/2023 Approved DAVID ANDERSON
Enclosure/Fence 5/3/2023 Approved MISAEL ESPARZA
Final 5/5/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved MISAEL ESPARZA
Equipment Noise Level 5/12/2023 Approved FELIPE PENICHE
Final 6/8/2023 OK to Issue CofO ROBERT GOLD