7030 W DE LONGPRE AVE 90028
Certificate Information: 7030 W DE LONGPRE AVE 90028
- Application / Permit
- 21047-20000-02323
- Plan Check / Job No.
- B21VN14339
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 11' X 20' POOL AND 8' X 8' SPA PER LA CITY STANDARD PLAN # 268.
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | PARISA ZAHABI |
| Corrections Issued | 10/21/2021 | PARISA ZAHABI |
| Plan Check Approved | 11/4/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 11/4/2021 | APPLICANT |
| Issued | 11/16/2021 | APPLICANT |
| CofO in Progress | 4/9/2022 | BRIAN SULLIVAN |
| CofO Issued | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 11/1/2021 | MICAELA TORRES-GIL |
| ZI | Cleared | 11/2/2021 | GRACIELA ACOSTA |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Gunite | 1/4/2022 | Corrections Issued | BRIAN SULLIVAN |
| Pre-Gunite | 1/5/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Pre-Gunite | 1/7/2022 | Approved | BRIAN SULLIVAN |
| Deputy Shotcrete | 1/10/2022 | Conditional Approval | BRIAN SULLIVAN |
| Deck | 3/8/2022 | Approved | BRIAN SULLIVAN |
| Enclosure/Fence | 3/8/2022 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Approved | BRIAN SULLIVAN |
| Final | 3/22/2022 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Pool Equipment Noise Test | 3/24/2022 | Approved | JUSTIN CURTIS |
| Final | 4/8/2022 | OK to Issue CofO | BRIAN SULLIVAN |