2035 N DAVIES WAY 90046
Certificate Information: 2035 N DAVIES WAY 90046
- Application / Permit
- 21047-20000-02274
- Plan Check / Job No.
- B21VN13970
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL THE (E) POOL TO 15' X 36', NEW BOND BEAM AND CHANGE THE SHAPE TO RECTANGULAR PER STANDARD PLAN 270 AND ENGINEERING.
- Permit Issued
- Issued on 5/4/2022
- Issuing Office
- Current Status
- CofO Issued on 11/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2021 | SERGIO MUNIZ |
| Corrections Issued | 10/25/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/18/2022 | SERGIO MUNIZ |
| Plan Check Approved | 4/1/2022 | SERGIO MUNIZ |
| Plan Check Approved | 4/15/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| Issued | 5/4/2022 | APPLICANT |
| CofO in Progress | 11/4/2024 | RAUL BARAJAS |
| Permit Finaled | 11/6/2024 | RUBEN SALAS |
| CofO Issued | 11/6/2024 | RUBEN SALAS |
| Permit Finaled | 11/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/18/2022 | SERGIO MUNIZ |
Contact Information
| Contractor | Abstract Pool Designs; Lic. No.: 670830-C53 | P O BOX 1388 UPLAND, CA 91785 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Mechanical | 6/2/2022 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 6/23/2022 | Conditional Approval | RAUL BARAJAS |
| Deck | 8/30/2022 | Approved | RAUL BARAJAS |
| Final | 7/5/2023 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Enclosure/Fence | 7/11/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 7/18/2023 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/18/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Enclosure/Fence | 7/31/2023 | Approved | STUART CHAPMAN |
| Final | 7/31/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 9/6/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 9/6/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 9/6/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 9/26/2023 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Final | 9/27/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 10/17/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 10/17/2023 | Approved | RAUL BARAJAS |
| Final | 8/23/2024 | Corrections Issued | RAUL BARAJAS |
| Pool Equipment Noise Test | 8/28/2024 | Approved | ANDEY CHAPARRO |
| Final | 11/4/2024 | OK to Issue CofO | RAUL BARAJAS |