5940 N RANCHITO AVE 91401
Certificate Information: 5940 N RANCHITO AVE 91401
- Application / Permit
- 21047-20000-02258
- Plan Check / Job No.
- B21VN13865
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePLAN. NEW POOL PER LA CITY STANDARD PLAN 268.
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2021 | KEVIN MORALES |
| Corrections Issued | 10/13/2021 | KEVIN MORALES |
| Plan Check Approved | 10/17/2021 | KEVIN MORALES |
| Issued | 10/28/2021 | APPLICANT |
| CofO in Progress | 12/19/2022 | RYAN SALAZAR |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Platner'S Pools; Lic. No.: 713747-C53 | 5862 CAPE HORN DRIVE AGOURA HILLS, CA 91301 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/10/2021 | Approved | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Approved | MICHEL ABAJAN |
| Pre-Gunite | 11/18/2021 | Approved | MICHEL ABAJAN |
| Grounding or Bonding | 1/28/2022 | Approved | RICHARD DOCKUS |
| Deck | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| Grounding or Bonding | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| Enclosure/Fence | 5/16/2022 | Corrections Issued | RAUL OLAGI |
| Enclosure/Fence | 5/18/2022 | Approved | RICHARD DOCKUS |
| Equipment Noise Level | 10/3/2022 | No Access for Inspection | FELIPE PENICHE |
| Equipment Noise Level | 10/13/2022 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 11/1/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Final | 11/15/2022 | Corrections Issued | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | ROBERT GOLD |
| Final | 12/16/2022 | OK to Issue CofO | RYAN SALAZAR |