254 N TIGERTAIL ROAD 90049
Certificate Information: 254 N TIGERTAIL ROAD 90049
- Application / Permit
- 21047-20000-02253
- Plan Check / Job No.
- B21VN13827
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 19' X 43' POOL W/ 9' X 10' SPA WITHIN POOL SHELL AND POOL COVER PER LA CITY STANDARD PLAN #267 AND DETAIL #: 501 AND 672
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2021 | JENNIFER LEE |
| Plan Check Approved | 10/20/2021 | JENNIFER LEE |
| Issued | 12/10/2021 | APPLICANT |
| CofO in Progress | 8/19/2023 | CARLOS MATAMOROS |
| Permit Finaled | 8/23/2023 | DANIEL ORRANTE |
| CofO Issued | 8/23/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/20/2021 | JENNIFER LEE |
Contact Information
| Contractor | Los Angeles Pool Builders Inc; Lic. No.: 857866-C53 | 9018 BALBOA BLVD SUITE 353 NORTHRIDGE, CA 91325 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 3/31/2022 | Approved | CARLOS MATAMOROS |
| Pool Piping | 4/4/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pre-Gunite | 4/4/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Shotcrete | 4/12/2022 | Conditional Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 7/29/2022 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 3/3/2023 | Approved | CARLOS MATAMOROS |
| Equipment Noise Level | 4/12/2023 | Approved | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 4/18/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Final | 4/21/2023 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 7/11/2023 | Approved | CARLOS MATAMOROS |
| Final | 7/11/2023 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/18/2023 | Approved | CARLOS MATAMOROS |
| Final | 8/18/2023 | OK to Issue CofO | CARLOS MATAMOROS |