5017 W ELMWOOD AVE 90004
Certificate Information: 5017 W ELMWOOD AVE 90004
- Application / Permit
- 21047-20000-02221
- Plan Check / Job No.
- B21VN13597
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 25' X 12' POOL W/ 6' X 7' SPA WITHIN POOL SHELL PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 10/7/2021
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | JENNIFER LEE |
| Plan Check Approved | 10/7/2021 | JENNIFER LEE |
| Issued | 10/7/2021 | APPLICANT |
| Building Plans Picked Up | 10/8/2021 | APPLICANT |
| CofO in Progress | 5/25/2022 | SHAVONNE ESPINOZA |
| No Progress | 7/25/2022 | RUBEN SALAS |
| CofO in Progress | 7/28/2022 | RUBEN SALAS |
| Permit Finaled | 7/29/2022 | DEROLD HAUFF |
| CofO Issued | 7/29/2022 | DEROLD HAUFF |
| Permit Finaled | 7/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 11/16/2021 | Approved | MASHEL JONGERT |
| Pre-Gunite | 11/16/2021 | Approved | MASHEL JONGERT |
| Deck | 3/14/2022 | Approved | CRAIG DAVIS |
| Grounding or Bonding | 3/14/2022 | Approved | CRAIG DAVIS |
| Deck | 3/18/2022 | Approved | SHAVONNE ESPINOZA |
| Enclosure/Fence | 3/18/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Grounding or Bonding | 3/18/2022 | Approved | SHAVONNE ESPINOZA |
| Enclosure/Fence | 3/25/2022 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 4/19/2022 | Approved | SHAVONNE ESPINOZA |
| Final | 4/19/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Pool Equipment Noise Test | 4/19/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 4/19/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Pool Equipment Noise Test | 4/21/2022 | Approved | ROBERT CHAVEZ |
| Final | 5/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 5/2/2022 | SGSOV Approved | SHAVONNE ESPINOZA |
| Final | 5/12/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 5/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 5/24/2022 | Approved | SHAVONNE ESPINOZA |
| Final | 5/24/2022 | OK to Issue CofO | SHAVONNE ESPINOZA |