10424 N EL DORADO AVE 91331

Certificate Information: 10424 N EL DORADO AVE 91331

Application / Permit
21047-20000-02218
Plan Check / Job No.
B21VN13565
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 26'-0" x 17'-0" POOL WITH A 8'-0" x 8'-0" SPA PER CITY STD. PLAN #268
Permit Issued
Issued on 11/29/2021
Issuing Office
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/6/2021 ALFRED RAMIREZ
Corrections Issued 10/6/2021 ALFRED RAMIREZ
Building Plans Picked Up 10/12/2021 APPLICANT
Applicant returned to address corrections 11/10/2021 ALFRED RAMIREZ
Issued 11/29/2021 APPLICANT
CofO in Progress 8/30/2022 MICHEL ABAJAN
Permit Finaled 8/30/2022 MICHAEL SMITH
CofO Issued 8/30/2022 MICHAEL SMITH
Permit Finaled 8/30/2022 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 978 NORTH AMEILA AVE      SAN DIMAS, CA 91773
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 3/1/2022 Approved MICHEL ABAJAN
Grounding or Bonding 3/1/2022 Approved MICHEL ABAJAN
Pool Piping 3/1/2022 Approved MICHEL ABAJAN
Pre-Gunite 3/1/2022 Approved MICHEL ABAJAN
Rough-Electrical 3/1/2022 Partial Approval MICHEL ABAJAN
Rough-Plumbing 3/1/2022 Partial Approval MICHEL ABAJAN
Deck 5/18/2022 Approved MICHEL ABAJAN
Enclosure/Fence 6/9/2022 Corrections Issued JOHN HAYES
Enclosure/Fence 7/20/2022 Approved MICHEL ABAJAN
Equipment Noise Level 8/8/2022 Approved FELIPE PENICHE
ELECTRICAL-Final 8/15/2022 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 8/15/2022 Approved MICHEL ABAJAN
Final 8/15/2022 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 8/15/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/15/2022 SGSOV Not Ready MICHEL ABAJAN
Final 8/19/2022 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Approved GREGG CUMMINGS
Final 8/29/2022 OK to Issue CofO MICHEL ABAJAN