13139 W BLOOMFIELD ST 91423
Certificate Information: 13139 W BLOOMFIELD ST 91423
- Application / Permit
- 21047-20000-02192
- Plan Check / Job No.
- B21VN13484
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 31' X 16' POOL WITH 8' X 9' SPA PER LA CITY STD PLAN # 268.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2021 | PARISA ZAHABI |
| Corrections Issued | 10/5/2021 | PARISA ZAHABI |
| Plan Check Approved | 2/18/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 2/22/2022 | APPLICANT |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 8/5/2022 | CHRISTOPHE COCHRAN |
| CofO in Progress | 8/5/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/5/2022 | RONALD MYRICK |
| CofO Issued | 8/5/2022 | RONALD MYRICK |
| Permit Finaled | 8/5/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/18/2022 | JOHN BACON |
Contact Information
| Contractor | Thomas Pools; Lic. No.: 945615-C53 | 28813 CARNATION COURT CASTAIC, CA 91384 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Approved | ARAM AVEDISIAN |
| Gas Piping or Gas Test | 3/21/2022 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 3/21/2022 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 3/21/2022 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 3/21/2022 | Approved | ARAM AVEDISIAN |
| Rough-Electrical | 3/21/2022 | Approved | ARAM AVEDISIAN |
| Deck | 5/9/2022 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 5/9/2022 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 7/6/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/21/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Equipment Noise Level | 7/26/2022 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 7/26/2022 | Approved | FELIPE PENICHE |
| Final | 8/3/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |