11659 W LA MAIDA ST 91601
Certificate Information: 11659 W LA MAIDA ST 91601
- Application / Permit
- 21047-20000-02186
- Plan Check / Job No.
- B21VN13442
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan NEW SWIMMING POOL / SPA
- Permit Issued
- Issued on 11/9/2021
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2021 | ZAW HAN |
| Corrections Issued | 10/14/2021 | ZAW HAN |
| Plan Check Approved | 10/26/2021 | ZAW HAN |
| Issued | 11/9/2021 | APPLICANT |
| CofO in Progress | 1/10/2023 | JACK KARGODORIAN |
| CofO Issued | 1/21/2023 | MICHAEL SMITH |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/14/2021 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 9/20/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Gas Piping or Gas Test | 9/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Grounding or Bonding | 9/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Pool Piping | 9/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Pre-Gunite | 9/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Electrical | 9/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Plumbing | 9/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 10/4/2022 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/14/2022 | Corrections Issued | JACK KARGODORIAN |
| Gas Piping or Gas Test | 10/14/2022 | Approved | JACK KARGODORIAN |
| Pre-Gunite | 10/14/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Rough-Electrical | 10/14/2022 | Approved | JACK KARGODORIAN |
| Rough-Plumbing | 10/14/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 10/21/2022 | Approved | JACK KARGODORIAN |
| Pool Piping | 10/21/2022 | Approved | JACK KARGODORIAN |
| Pre-Gunite | 10/21/2022 | Approved | JACK KARGODORIAN |
| Rough-Electrical | 10/21/2022 | Approved | JACK KARGODORIAN |
| Rough-Plumbing | 10/21/2022 | Approved | JACK KARGODORIAN |
| Deck | 10/31/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Grounding or Bonding | 10/31/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Gunite | 10/31/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Deck | 11/2/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Grounding or Bonding | 11/2/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Gunite | 11/2/2022 | Approved | JACK KARGODORIAN |
| Deputy Shotcrete | 11/3/2022 | Approved | JACK KARGODORIAN |
| Deck | 11/14/2022 | Corrections Issued | JACK KARGODORIAN |
| Deck | 11/15/2022 | Approved | JACK KARGODORIAN |
| Enclosure/Fence | 1/6/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 1/6/2023 | Corrections Issued | JACK KARGODORIAN |
| Pool Equipment Noise Test | 1/6/2023 | Approved | ALFREDO FLORES |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Approved | JACK KARGODORIAN |
| Enclosure/Fence | 1/10/2023 | Approved | JACK KARGODORIAN |
| Final | 1/10/2023 | OK to Issue CofO | JACK KARGODORIAN |