2302 S CAMDEN AVE 90064
Certificate Information: 2302 S CAMDEN AVE 90064
- Application / Permit
- 21047-20000-02184
- Plan Check / Job No.
- B21VN13434
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 28' X 14' SWIMMING POOL WITH 9' X 7' ATTACHED SPA AS PER STANDARD PLAN # 268 - SEE COMMENTS
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2021 | RARES BODEA |
| Corrections Issued | 10/5/2021 | RARES BODEA |
| Plan Check Approved | 11/1/2021 | RARES BODEA |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| CofO in Progress | 1/11/2023 | JUAN VALENZUELA |
| Permit Finaled | 1/19/2023 | DANIEL ORRANTE |
| CofO Issued | 1/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/19/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/12/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/12/2021 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 10/29/2021 | RARES BODEA |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/17/2021 | Approved | OGANES TARAKHCHYAN |
| Deputy Shotcrete | 12/22/2021 | Conditional Approval | JOHNNY MIRANDA |
| Grounding or Bonding | 1/10/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Enclosure/Fence | 1/20/2022 | Approved | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Approved | EVAN COOPER |
| Final | 3/2/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Approved | EVAN COOPER |
| Equipment Noise Level | 3/3/2022 | Approved | ROBERT CHAVEZ |
| Final | 3/8/2022 | Conditional Approval | EVAN COOPER |
| Special/Order Compliance | 3/29/2022 | Corrections Issued | EVAN COOPER |