13016 W CHANDLER BLVD 91401

Certificate Information: 13016 W CHANDLER BLVD 91401

Application / Permit
21047-20000-02181
Plan Check / Job No.
B21VN13428
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW (28'x 15') SWIMMING POOL WITH (15'z 6') SPA. PER LA STD PLAN #268.
Permit Issued
Issued on 6/2/2022
Issuing Office
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 TROY DEGUZMAN
Corrections Issued 10/24/2021 TROY DEGUZMAN
Quality Review Completed 11/8/2021 OMID HEDAYAT
Building Plans Picked Up 11/9/2021 APPLICANT
Applicant returned to address corrections 4/27/2022 TROY DEGUZMAN
Applicant returned to address corrections 5/26/2022 TROY DEGUZMAN
Plan Check Approved 6/2/2022 TROY DEGUZMAN
Issued 6/2/2022 APPLICANT
CofO in Progress 7/12/2024 OGANES TARAKHCHYAN
CofO in Progress 9/10/2024 OGANES TARAKHCHYAN
CofO in Progress 9/24/2024 OGANES TARAKHCHYAN
CofO Issued 10/3/2024 DANIEL ORRANTE
Permit Finaled 10/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Hold Cleared 7/5/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2022 Not Ready for Inspection RAFAEL CORTES
Rough-Plumbing 9/16/2022 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 3/23/2023 Corrections Issued KIRK SANDERS
Rough-Electrical 3/23/2023 Approved KIRK SANDERS
Rough-Plumbing 3/23/2023 Not Ready for Inspection KIRK SANDERS
Rough-Electrical 3/29/2023 No Access for Inspection KIRK SANDERS
Rough-Plumbing 3/29/2023 No Access for Inspection KIRK SANDERS
Excavation/Setback/Form/Re-Bar 4/3/2023 Approved KIRK SANDERS
Rough-Electrical 4/3/2023 Approved KIRK SANDERS
Rough-Plumbing 4/3/2023 Approved KIRK SANDERS
Deputy Shotcrete 4/25/2023 Conditional Approval KIRK SANDERS
Deck 10/16/2023 Partial Approval CHRISTOPHER ROJAS
Enclosure/Fence 5/20/2024 Corrections Issued OGANES TARAKHCHYAN
Enclosure/Fence 5/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Enclosure/Fence 5/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Enclosure/Fence 6/4/2024 Corrections Issued SALVADOR MARTINEZ
Enclosure/Fence 6/10/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 7/11/2024 Approved OGANES TARAKHCHYAN
Final 7/11/2024 OK to Issue CofO OGANES TARAKHCHYAN
PLUMBING-Final 7/11/2024 Approved OGANES TARAKHCHYAN
Pre-Gunite 7/11/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved OGANES TARAKHCHYAN
Equipment Noise Level 9/23/2024 Approved ALFREDO FLORES
Pool Equipment Noise Test 9/23/2024 Approved ALFREDO FLORES