101 N HUDSON AVE 90004
Certificate Information: 101 N HUDSON AVE 90004
- Application / Permit
- 21047-20000-02164
- Plan Check / Job No.
- B21VN13306
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL (52'-0"x22'-0")
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- CofO Issued on 4/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 10/5/2021 | APPLICANT |
| Corrections Issued | 10/26/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 10/28/2021 | MOHAMMAD ESMAILI |
| Issued | 11/3/2021 | APPLICANT |
| CofO in Progress | 3/23/2023 | RICHARD DOCKUS |
| No Progress | 3/30/2023 | SCOTT FINNILA |
| CofO in Progress | 4/4/2023 | SCOTT FINNILA |
| CofO Issued | 4/7/2023 | DEROLD HAUFF |
| Permit Finaled | 4/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 10/12/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Wavecrest Pools Inc; Lic. No.: 881346-C53 | 5320 DERRY AVENUE SUITE B AGOURA HILLS, CA 91301 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Approved | ARTHUR SARGSYAN |
| Pool Piping | 12/13/2021 | Approved | ARTHUR SARGSYAN |
| Pre-Gunite | 12/13/2021 | Approved | ARTHUR SARGSYAN |
| Rough-Electrical | 12/13/2021 | Approved | ARTHUR SARGSYAN |
| Rough-Plumbing | 12/13/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Shotcrete | 12/20/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Shotcrete | 5/23/2022 | Conditional Approval | ADAM ESCOTO |
| Enclosure/Fence | 7/29/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deck | 8/2/2022 | Approved | RYAN SALAZAR |
| Grounding or Bonding | 8/2/2022 | Approved | RYAN SALAZAR |
| Gas Piping or Gas Test | 8/4/2022 | Approved | MICHAEL LEWIS |
| Enclosure/Fence | 12/1/2022 | Corrections Issued | RICHARD DOCKUS |
| Enclosure/Fence | 12/6/2022 | Corrections Issued | STUART CHAPMAN |
| Enclosure/Fence | 12/7/2022 | Approved | SCOTT FINNILA |
| Enclosure/Fence | 12/7/2022 | Corrections Issued | SCOTT FINNILA |
| Final | 2/22/2023 | No Access for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Approved | RICHARD DOCKUS |
| Final | 3/3/2023 | Corrections Issued | RICHARD DOCKUS |
| Final | 3/16/2023 | OK to Issue CofO | RICHARD DOCKUS |