13445 W TIARA ST 91401
Certificate Information: 13445 W TIARA ST 91401
- Application / Permit
- 21047-20000-02157
- Plan Check / Job No.
- B21VN13265
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17'-0" x 32'-0" POOL WITH 6'-0" x 7'-0" SPA PER LA CITY STANDARD DETAIL# 268.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 9/30/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 2/2/2022 | SARKIS HARABEDIAN |
| Issued | 2/3/2022 | APPLICANT |
| Building Plans Picked Up | 2/4/2022 | APPLICANT |
| CofO in Progress | 11/14/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Sutton Pools & Hardscape Inc; Lic. No.: 943561-C53 | 693 LAKEVIEW CANYON ROAD WESTLAKE VILLAGE, CA 91362 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 5/27/2022 | Conditional Approval | CALEB MEISTER |
| Gas Piping or Gas Test | 6/17/2022 | Approved | RAFAEL CORTES |
| Rough-Electrical | 6/17/2022 | Approved | RAFAEL CORTES |
| Deck | 7/1/2022 | Partial Approval | RAFAEL CORTES |
| Deck | 8/8/2022 | Approved | RAFAEL CORTES |
| Enclosure/Fence | 10/5/2022 | Corrections Issued | RAFAEL CORTES |
| Enclosure/Fence | 10/18/2022 | Approved | CALEB MEISTER |
| Pool Equipment Noise Test | 11/1/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 11/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 11/3/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 11/10/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |