108 S LAS PALMAS AVE 90004
Certificate Information: 108 S LAS PALMAS AVE 90004
- Application / Permit
- 21047-20000-02155
- Plan Check / Job No.
- B21VN13234
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 27'X18' SWIMMING POOL W/ 8'X7' SPA PER CITY STD PLAN #265. SEE COMMENTS.
- Permit Issued
- Issued on 10/25/2021
- Issuing Office
- Current Status
- CofO Issued on 11/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 10/1/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/20/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/21/2021 | APPLICANT |
| Issued | 10/25/2021 | APPLICANT |
| CofO in Progress | 10/30/2023 | JOSEPH MCGARRY |
| Permit Finaled | 11/3/2023 | DEROLD HAUFF |
| CofO Issued | 11/3/2023 | DEROLD HAUFF |
| Permit Finaled | 11/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 10/13/2021 | DANG NGUYEN |
| HPOZ | Cleared | 10/13/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 10/13/2021 | DANG NGUYEN |
Contact Information
| Contractor | Gwp Services; Lic. No.: 974163-C53 | 5632 VAN NUYS BLVD #427 VAN NUYS, CA 91401 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/14/2022 | Approved | ARTHUR SARGSYAN |
| Deputy Shotcrete | 3/15/2022 | Approved | ARTHUR SARGSYAN |
| Deck | 8/12/2022 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 8/23/2022 | Approved | STUART CHAPMAN |
| Final | 8/23/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Not Ready | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 11/14/2022 | Approved | JOSEPH MCGARRY |
| Final | 11/14/2022 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Not Ready | JOSEPH MCGARRY |
| Equipment Noise Level | 11/17/2022 | Approved | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Rough-Electrical | 3/13/2023 | Corrections Issued | RICHARD DOCKUS |
| Rough-Plumbing | 3/13/2023 | Approved | RICHARD DOCKUS |
| Final | 10/25/2023 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Approved | JOSEPH MCGARRY |