- New swimming pool and spa per city of Los Angeles standard plan # 268.
- Permit Issued
- Issued on 12/28/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2021 | HELEN NGUYEN |
| Corrections Issued | 10/4/2021 | HELEN NGUYEN |
| Plan Check Approved | 12/22/2021 | JOE VO |
| Issued | 12/28/2021 | APPLICANT |
| CofO in Progress | 8/18/2022 | THOMAS FINNILA |
| CofO in Progress | 8/18/2022 | THOMAS FINNILA |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 11/22/2021 | DANG NGUYEN |
| Construction near power lines | Cleared | 12/21/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/14/2022 | Conditional Approval | THOMAS FINNILA |
| Grounding or Bonding | 5/26/2022 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 7/8/2022 | Approved | STEPHANIE SWANSON |
| Equipment Noise Level | 8/3/2022 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 8/3/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Approved | THOMAS FINNILA |
| Final | 8/10/2022 | Corrections Issued | THOMAS FINNILA |
| Pre-Gunite | 8/10/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/10/2022 | SGSOV Approved | THOMAS FINNILA |
| Final | 8/16/2022 | OK to Issue CofO | THOMAS FINNILA |