21453 W ALAMO ST 91364
Certificate Information: 21453 W ALAMO ST 91364
- Application / Permit
- 21047-20000-02139
- Plan Check / Job No.
- B21VN13111
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan new 7' x 11' x 3' 6" Pool
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2021 | DANIEL YIP |
| Corrections Issued | 9/30/2021 | DANIEL YIP |
| Applicant returned to address corrections | 12/23/2021 | DANIEL YIP |
| Applicant returned to address corrections | 12/27/2021 | DANIEL YIP |
| Applicant returned to address corrections | 12/29/2021 | DANIEL YIP |
| Plan Check Approved | 12/29/2021 | DANIEL YIP |
| No Progress | 12/29/2021 | DANIEL YIP |
| Plan Check Approved | 2/7/2022 | DANIEL YIP |
| Issued | 2/10/2022 | APPLICANT |
| CofO in Progress | 6/15/2022 | PETER FOLLING |
| No Progress | 7/5/2022 | ROBERT GOLD |
| CofO in Progress | 8/16/2022 | PETER FOLLING |
| Permit Finaled | 8/16/2022 | JOHN JANSON |
| CofO Issued | 8/16/2022 | JOHN JANSON |
| Permit Finaled | 8/16/2022 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/23/2021 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: NA67656 | , |
| Engineer | Shahidi,, Saeed; Lic. No.: C51711 | 25422 TRABUCO RD #105 LAKE FOREST, CA 92630 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 3/3/2022 | Corrections Issued | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Not Ready for Inspection | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 3/25/2022 | Approved | PETER FOLLING |
| Gas Piping or Gas Test | 3/25/2022 | Not Ready for Inspection | PETER FOLLING |
| Pre-Gunite | 3/25/2022 | Approved | PETER FOLLING |
| Rough-Electrical | 3/25/2022 | Approved | PETER FOLLING |
| Rough-Plumbing | 3/25/2022 | Approved | PETER FOLLING |
| Gas Piping or Gas Test | 4/14/2022 | Approved | DAVID SCANTLIN |
| Rough-Plumbing | 4/14/2022 | Partial Approval | DAVID SCANTLIN |
| Enclosure/Fence | 5/6/2022 | Corrections Issued | PETER FOLLING |
| Enclosure/Fence | 5/10/2022 | Approved | PETER FOLLING |
| Grounding or Bonding | 5/10/2022 | Approved | PETER FOLLING |
| Final | 5/17/2022 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Approved | VINCENT HANLEY |
| Final | 6/15/2022 | OK to Issue CofO | PETER FOLLING |
| Pool Equipment Noise Test | 7/6/2022 | No Access for Inspection | ALFREDO FLORES |
| Pool Equipment Noise Test | 7/26/2022 | Approved | ALFREDO FLORES |