13553 W MONTAGUE ST 91331
Certificate Information: 13553 W MONTAGUE ST 91331
- Application / Permit
- 21047-20000-02113
- Plan Check / Job No.
- B21VN12855
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 13' x 28' POOL AND 8' x 13' SPA.
- Permit Issued
- Issued on 11/17/2021
- Issuing Office
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2021 | LUIS RINCON |
| Corrections Issued | 10/5/2021 | LUIS RINCON |
| Applicant returned to address corrections | 10/29/2021 | LUIS RINCON |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| Plan Check Approved | 11/16/2021 | LUIS RINCON |
| Issued | 11/17/2021 | APPLICANT |
| CofO in Progress | 7/25/2022 | DAVID MATSON |
| CofO Issued | 7/28/2022 | MICHAEL SMITH |
| Permit Finaled | 7/28/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/16/2021 | JOHN BACON |
| Construction within easement | Cleared | 11/16/2021 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Mechanical | 4/8/2022 | Partial Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Corrections Issued | GREGG CUMMINGS |
| Grading Pre-Inspection | 4/12/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 4/12/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Gunite | 4/12/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Approved | GREGG CUMMINGS |
| Pre-Gunite | 4/18/2022 | Approved | GREGG CUMMINGS |
| Rough-Electrical | 4/18/2022 | Approved | GREGG CUMMINGS |
| Rough-Plumbing | 4/18/2022 | Approved | GREGG CUMMINGS |
| Enclosure/Fence | 6/27/2022 | Corrections Issued | GREGG CUMMINGS |
| Enclosure/Fence | 6/30/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Enclosure/Fence | 7/6/2022 | Approved | GREGG CUMMINGS |
| Final | 7/18/2022 | OK to Issue CofO | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | GREGG CUMMINGS |