6141 N SIMPSON AVE 91606
Certificate Information: 6141 N SIMPSON AVE 91606
- Application / Permit
- 21047-20000-02098
- Plan Check / Job No.
- B21VN12804
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17'-0" x 24'-0" POOL AND 9'-0" x 9'-0" SPA PER CITY STD. PLAN #268
- Permit Issued
- Issued on 10/4/2021
- Issuing Office
- Current Status
- CofO Issued on 12/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2021 | ALFRED RAMIREZ |
| Corrections Issued | 9/22/2021 | ALFRED RAMIREZ |
| Issued | 10/4/2021 | APPLICANT |
| Building Plans Picked Up | 10/6/2021 | APPLICANT |
| CofO in Progress | 10/31/2022 | JOHN HAYES |
| CofO in Progress | 12/13/2022 | JOHN HAYES |
| CofO Issued | 12/19/2022 | MICHAEL SMITH |
| Permit Finaled | 12/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/10/2022 | Approved | ARAM AVEDISIAN |
| Gas Piping or Gas Test | 2/10/2022 | Partial Approval | ARAM AVEDISIAN |
| Grounding or Bonding | 2/10/2022 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 2/10/2022 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 2/10/2022 | Approved | ARAM AVEDISIAN |
| Deck | 5/24/2022 | Approved | CALEB MEISTER |
| Grounding or Bonding | 5/24/2022 | Approved | CALEB MEISTER |
| Grounding or Bonding | 5/26/2022 | Approved | CALEB MEISTER |
| Deck | 6/29/2022 | Approved | JOHN HAYES |
| Enclosure/Fence | 8/12/2022 | Approved | JOHN HAYES |
| Final | 8/30/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Not Ready | JOHN HAYES |
| Pool Equipment Noise Test | 9/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/30/2022 | Not Ready for Inspection | JOHN HAYES |
| Pool Equipment Noise Test | 9/30/2022 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Not Ready | JOHN HAYES |
| Final | 10/6/2022 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Approved | JOHN HAYES |
| Final | 10/31/2022 | OK to Issue CofO | JOHN HAYES |