11442 N VALJEAN AVE 91344
Certificate Information: 11442 N VALJEAN AVE 91344
- Application / Permit
- 21047-20000-02093
- Plan Check / Job No.
- B21VN12785
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30' 6" X 10' IRR.-SHAPED SWIMMING POOL WITH ATTACHED 6' DIAMETER SPA. ALL WORK DONE PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 9/22/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/22/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/4/2022 | GURUNATH NESARAJAH |
| Issued | 3/10/2022 | APPLICANT |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| CofO in Progress | 8/5/2022 | DEANDRE HOFFMAN |
| No Progress | 8/22/2022 | ROBERT GOLD |
| CofO in Progress | 8/30/2022 | ROBERT GOLD |
| Permit Finaled | 8/30/2022 | MICHAEL SMITH |
| CofO Issued | 8/30/2022 | MICHAEL SMITH |
| Permit Finaled | 8/30/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/4/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Aqua Care; Lic. No.: 927181-C53 | 537 SOMBRERO RD MONROVIA, CA 91016 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2022 | Approved | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 4/13/2022 | Not Ready for Inspection | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 4/20/2022 | Approved | JAVIER RAMOS JR |
| Gas Piping or Gas Test | 4/20/2022 | Partial Approval | JAVIER RAMOS JR |
| Rough-Electrical | 4/20/2022 | Approved | JAVIER RAMOS JR |
| Rough-Plumbing | 4/20/2022 | Approved | JAVIER RAMOS JR |
| Deputy Shotcrete | 5/12/2022 | Conditional Approval | JAVIER RAMOS JR |
| Grounding or Bonding | 6/8/2022 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 6/27/2022 | Approved | JAVIER RAMOS JR |
| Final | 7/6/2022 | Corrections Issued | DANIEL ORRANTE |
| Pre-Gunite | 7/6/2022 | Approved | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | DANIEL ORRANTE |
| Pre-Inspection | 7/11/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Final | 8/5/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Pool Equipment Noise Test | 8/24/2022 | Approved | ALFREDO FLORES |