2168 N PRINCETON AVE 90026

Certificate Information: 2168 N PRINCETON AVE 90026

Application / Permit
21047-20000-02078
Plan Check / Job No.
B21VN12720
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16'x28' POOL W/ 6'x8' SPA AND ATT. IRR. SHAPED CONCRETE DECK; ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 8/26/2022
Issuing Office
Valley
Current Status
Issued on 8/26/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 SEAN SHAHMIRI
Corrections Issued 10/20/2021 SEAN SHAHMIRI
Quality Review Completed 10/27/2021 OMID HEDAYAT
Building Plans Picked Up 10/28/2021 APPLICANT
Plan Check Approved 8/18/2022 SEAN SHAHMIRI
Issued 8/26/2022 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 7/25/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/12/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 8/16/2022 CINDY QI

Contact Information

Contractor Emerge Pools Inc; Lic. No.: 1010243-B 14740 VINCENNES STREET      PANORAMA CITY, CA 91402
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Shniderman,, Jason Bernard; Lic. No.: C20524 16000 SHERMAN WAY #234      VAN NUYS, CA 91607

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/28/2023 Corrections Issued THOMAS LOGRASSO
Deputy Other (see comments) 9/1/2023 Conditional Approval THOMAS LOGRASSO
Deputy Shotcrete 9/5/2023 Conditional Approval THOMAS LOGRASSO
Pre-Gunite 10/2/2023 Partial Approval THOMAS LOGRASSO
Deputy Shotcrete 10/10/2023 Conditional Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 12/13/2023 Conditional Approval THOMAS LOGRASSO
Deck 1/8/2024 Not Ready for Inspection THOMAS LOGRASSO
Deck 1/10/2024 Corrections Issued THOMAS LOGRASSO
Gas Piping or Gas Test 1/29/2024 Approved HAMIK HARTOUNIAN
Rough-Electrical 1/29/2024 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/12/2024 Not Ready for Inspection THOMAS LOGRASSO
Deputy Drilled-In Anchors 4/9/2024 Conditional Approval THOMAS LOGRASSO
Deputy Other (see comments) 4/9/2024 Conditional Approval THOMAS LOGRASSO
Deck 4/18/2024 Conditional Approval BRENDAN MORELLI
Deputy Other (see comments) 4/19/2024 Conditional Approval CRAIG VAUGHAN
Pre-Inspection 6/10/2024 Partial Inspection HAMIK HARTOUNIAN
Enclosure/Fence 6/27/2024 Partial Approval HAMIK HARTOUNIAN
Enclosure/Fence 7/1/2024 Partial Approval HAMIK HARTOUNIAN
Equipment Noise Level 8/23/2024 Approved ANDEY CHAPARRO
Excavation/Setback/Form/Re-Bar 6/24/2025 Approved HAMIK HARTOUNIAN
Final 6/24/2025 Corrections Issued HAMIK HARTOUNIAN
Pre-Gunite 6/24/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Approved HAMIK HARTOUNIAN
Final 1/29/2026 Not Ready for Inspection WILLIAM SIERRA