6442 W RIGGS PL 90045
Certificate Information: 6442 W RIGGS PL 90045
- Application / Permit
- 21047-20000-02050
- Plan Check / Job No.
- B21VN12387
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 26' X 13' SWIMMING POOL AND 8' X 13' SPA PER LA CITY STANDARD PLAN 265 WITH SUPPLEENTAL DETAILS PER ENGINEERING.
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Issued on 10/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2021 | OMAR GARNICA |
| Corrections Issued | 9/14/2021 | OMAR GARNICA |
| Plan Check Approved | 4/6/2022 | OMAR GARNICA |
| Building Plans Picked Up | 4/20/2022 | APPLICANT |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 10/24/2023 | HERBERT GIRON |
| Permit Finaled | 10/26/2023 | DANIEL ORRANTE |
| CofO Issued | 10/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/22/2022 | Corrections Issued | DAVID FEILER |
| Pool Piping | 7/22/2022 | Conditional Approval | DAVID FEILER |
| Pre-Gunite | 7/22/2022 | Not Ready for Inspection | DAVID FEILER |
| Rough-Electrical | 7/22/2022 | Conditional Approval | DAVID FEILER |
| Rough-Plumbing | 7/22/2022 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 7/28/2022 | Conditional Approval | HERBERT GIRON |
| Pre-Gunite | 7/28/2022 | Approved | HERBERT GIRON |
| Rough-Electrical | 7/28/2022 | Approved | HERBERT GIRON |
| Rough-Plumbing | 7/28/2022 | Approved | HERBERT GIRON |
| Deputy Shotcrete | 8/9/2022 | Conditional Approval | HERBERT GIRON |
| Gas Piping or Gas Test | 3/15/2023 | Corrections Issued | HERBERT GIRON |
| Gas Piping or Gas Test | 3/24/2023 | Corrections Issued | HERBERT GIRON |
| Gas Piping or Gas Test | 3/31/2023 | Approved | HERBERT GIRON |
| Deck | 7/20/2023 | Partial Approval | HERBERT GIRON |
| Grounding or Bonding | 7/20/2023 | Partial Approval | HERBERT GIRON |
| Deck | 8/30/2023 | No Access for Inspection | TEMISTOCLES CAAL |
| Grounding or Bonding | 8/30/2023 | No Access for Inspection | TEMISTOCLES CAAL |
| Enclosure/Fence | 9/20/2023 | Approved | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 9/27/2023 | Approved | HERBERT GIRON |
| Final | 9/27/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Approved | HERBERT GIRON |
| Pool Equipment Noise Test | 9/28/2023 | Approved | JAMES VORHIS |
| Final | 10/17/2023 | Conditional Approval | HERBERT GIRON |
| Final | 10/23/2023 | OK to Issue CofO | HERBERT GIRON |