17853 W PALORA ST 91316
Certificate Information: 17853 W PALORA ST 91316
- Application / Permit
- 21047-20000-02044
- Plan Check / Job No.
- B21VN12346
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 30' POOL W/ 8' X 8' SPA PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- CofO Issued on 1/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2021 | JENNIFER LEE |
| Corrections Issued | 9/14/2021 | JENNIFER LEE |
| Plan Check Approved | 9/30/2021 | JENNIFER LEE |
| Issued | 10/5/2021 | APPLICANT |
| Building Plans Picked Up | 10/6/2021 | APPLICANT |
| CofO in Progress | 1/17/2023 | DAVID SANDOVAL |
| CofO Issued | 1/23/2023 | JOHN JANSON |
| Permit Finaled | 1/23/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/14/2021 | JENNIFER LEE |
| Construction near power lines | Cleared | 9/23/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 10/20/2021 | Approved | VINCENT HANLEY |
| Pre-Gunite | 10/20/2021 | Approved | VINCENT HANLEY |
| Rough-Electrical | 10/20/2021 | Corrections Issued | VINCENT HANLEY |
| Rough-Plumbing | 10/20/2021 | Approved | VINCENT HANLEY |
| Deputy Shotcrete | 10/22/2021 | Conditional Approval | DAVID SANDOVAL |
| Deck | 11/15/2021 | Approved | DAVID SANDOVAL |
| Enclosure/Fence | 1/18/2022 | Approved | DAVID SANDOVAL |
| Equipment Noise Level | 2/9/2022 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 2/10/2022 | Approved | DAVID SANDOVAL |
| Final | 2/10/2022 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Approved | DAVID SANDOVAL |
| Final | 3/1/2022 | Partial Approval | DAVID SANDOVAL |
| Final | 1/17/2023 | OK to Issue CofO | DAVID SANDOVAL |