20787 W LIANA CT 91326

Certificate Information: 20787 W LIANA CT 91326

Application / Permit
21047-20000-02039
Plan Check / Job No.
B21VN12315
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 32' X 17' SWIMMING POOL WITH 7' X 7' SPA. WORK PER STANDARD PLAN #268.
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
CofO Issued on 3/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2021 APPLICANT
Assigned to Plan Check Engineer 9/13/2021 ROSENDO MEDINA
Corrections Issued 9/13/2021 ROSENDO MEDINA
Applicant returned to address corrections 10/12/2021 ROSENDO MEDINA
Plan Check Approved 10/12/2021 ROSENDO MEDINA
Building Plans Picked Up 10/13/2021 APPLICANT
Issued 11/4/2021 APPLICANT
CofO in Progress 3/18/2022 DAVID SCANTLIN
Permit Finaled 3/18/2022 JOHN JANSON
CofO Issued 3/18/2022 JOHN JANSON
Permit Finaled 3/18/2022 JOHN JANSON

Permit Application Clearance Information

"T" removal Cleared 9/29/2021 RICHARD REASER
Tract Map conditions Cleared 9/29/2021 RICHARD REASER
Tract Map conditions Cleared 9/29/2021 RICHARD REASER
ZA Case Cleared 9/29/2021 RICHARD REASER
ZA Case Cleared 9/29/2021 RICHARD REASER
Grading Pre-Inspection Cleared 10/12/2021 ROSENDO MEDINA

Contact Information

Contractor Gonzalez Uriel; Lic. No.: 908419-B 10330 TELFAIR AVENUE      PACOIMA, CA 91331
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2021 Partial Approval DAVID SCANTLIN
Gas Piping or Gas Test 11/15/2021 Approved DAVID SCANTLIN
Pool Piping 11/15/2021 Approved DAVID SCANTLIN
Pre-Gunite 11/15/2021 Partial Approval DAVID SCANTLIN
Pre-Inspection 11/15/2021 Approved DAVID SCANTLIN
Rough-Electrical 11/15/2021 Approved DAVID SCANTLIN
Rough-Plumbing 11/15/2021 Approved DAVID SCANTLIN
Deck 12/4/2021 Approved STEVEN BACK
Special/Order Compliance 12/4/2021 Approved STEVEN BACK
Grounding or Bonding 12/6/2021 Approved DAVID SCANTLIN
Enclosure/Fence 1/25/2022 Approved DAVID SCANTLIN
Pre-Gunite 1/25/2022 Approved DAVID SCANTLIN
Equipment Noise Level 2/18/2022 Approved ALFREDO FLORES
Final 2/22/2022 Corrections Issued DAVID SCANTLIN
PLUMBING-Final 2/22/2022 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 3/1/2022 Approved DAVID SCANTLIN
Final 3/1/2022 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Approved DAVID SCANTLIN
Final 3/10/2022 Not Ready for Inspection DAVID SCANTLIN
Final 3/17/2022 Partial Approval HENRY KIM
Final 3/18/2022 OK to Issue CofO DAVID SCANTLIN