4132 N WILKINSON AVE 91604
Certificate Information: 4132 N WILKINSON AVE 91604
- Application / Permit
- 21047-20000-02029
- Plan Check / Job No.
- B21VN12249
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW (15'-0"x30'-0") POOL AND (7'-0"x5'-0") SPA PER STD. PLAN #268, AND POOL COVER DETAILS
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- Issued on 1/10/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2021 | PETER MOSESIAN |
| Corrections Issued | 9/10/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 9/15/2021 | APPLICANT |
| Issued | 1/10/2022 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/11/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Los Angeles Pool Builders Inc; Lic. No.: 857866-C53 | 9018 BALBOA BLVD SUITE 353 NORTHRIDGE, CA 91325 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/24/2022 | Approved | ARAM AVEDISIAN |
| Gas Piping or Gas Test | 1/24/2022 | Partial Approval | ARAM AVEDISIAN |
| Grounding or Bonding | 1/24/2022 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 1/24/2022 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 1/24/2022 | Approved | ARAM AVEDISIAN |
| Rough-Electrical | 1/24/2022 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 1/25/2022 | Conditional Approval | ARAM AVEDISIAN |
| Enclosure/Fence | 3/8/2022 | Corrections Issued | ARAM AVEDISIAN |
| Grounding or Bonding | 3/8/2022 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 3/11/2022 | Approved | ARAM AVEDISIAN |
| Final | 4/4/2022 | Partial Approval | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | ARAM AVEDISIAN |