455 N BUNDY DR 90049
Certificate Information: 455 N BUNDY DR 90049
- Application / Permit
- 21047-20000-02027
- Plan Check / Job No.
- B21VN12239
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL (52'-0" X 17'-0") AND SPA. (7'-0"x7'-0") per standard plan #268
- Permit Issued
- Issued on 10/29/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/1/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 10/5/2021 | APPLICANT |
| Plan Check Approved | 10/28/2021 | MOHAMMAD ESMAILI |
| Issued | 10/29/2021 | APPLICANT |
| CofO in Progress | 8/23/2022 | MICHAEL PELHAM |
| Permit Finaled | 8/23/2022 | DANIEL ORRANTE |
| CofO Issued | 8/23/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/1/2021 | MOHAMMAD ESMAILI |
| Construction near power lines | Cleared | 10/15/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2021 | Conditional Approval | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 12/1/2021 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 12/1/2021 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 12/1/2021 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 12/1/2021 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 12/3/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deck | 4/7/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 4/7/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Enclosure/Fence | 6/9/2022 | Corrections Issued | MICHAEL PELHAM |
| Enclosure/Fence | 6/10/2022 | Approved | CARLOS MATAMOROS |
| Final | 6/24/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 6/28/2022 | Corrections Issued | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 6/28/2022 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 7/6/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 8/23/2022 | Conditional Approval | MICHAEL PELHAM |