4802 N VANALDEN AVE 91356
Certificate Information: 4802 N VANALDEN AVE 91356
- Application / Permit
- 21047-20000-02025
- Plan Check / Job No.
- B21VN12223
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL (E) SWIMMING POOL. ADD 20' X 10' TO ENLARGE POOL AND ADD 6' X 8' SPA PER STANDARD PLAN #268 AND ENGINEER DETAIL.
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 12/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 9/9/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 9/22/2021 | JEROME MAGAT PALMA |
| Issued | 9/22/2021 | APPLICANT |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| Permit Finaled | 12/13/2025 | MICHAEL PELHAM |
| CofO Issued | 12/13/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/13/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/9/2021 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Custom Derian Pools & Construction; Lic. No.: 977981-C53 | PO BOX 1352 MOORPARK, CA 93020 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/24/2021 | Approved | DAVID SANDOVAL |
| Deputy Shotcrete | 9/28/2021 | Partial Approval | DAVID SANDOVAL |
| Gas Piping or Gas Test | 10/4/2021 | Approved | DAVID SANDOVAL |
| Rough-Electrical | 10/4/2021 | Approved | DAVID SANDOVAL |
| Deck | 11/16/2021 | Approved | DAVID SANDOVAL |
| Enclosure/Fence | 12/30/2021 | Approved | PETER FOLLING |
| Equipment Noise Level | 1/26/2022 | Approved | ALFREDO FLORES |
| Final | 1/27/2022 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 2/3/2022 | Approved | DAVID SANDOVAL |
| Final | 2/3/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Final | 2/3/2022 | Approved | DAVID SANDOVAL |