23446 W JUSTICE ST 91304
Certificate Information: 23446 W JUSTICE ST 91304
- Application / Permit
- 21047-20000-02008
- Plan Check / Job No.
- B21VN12032
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 18'-0" X 32'-0" POOL WITH 5' X 10' SPA PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 10/14/2021
- Issuing Office
- Current Status
- CofO Issued on 8/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2021 | JESSE ARELLANO |
| Corrections Issued | 9/7/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 9/30/2021 | JESSE ARELLANO |
| Plan Check Approved | 10/8/2021 | JESSE ARELLANO |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| Issued | 10/14/2021 | APPLICANT |
| CofO in Progress | 8/23/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 8/26/2022 | JOHN JANSON |
| CofO Issued | 8/26/2022 | JOHN JANSON |
| Permit Finaled | 8/26/2022 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/26/2021 | Corrections Issued | DAVID STEPANYAN |
| Special/Order Compliance | 10/26/2021 | Corrections Issued | DAVID STEPANYAN |
| Pre-Gunite | 11/19/2021 | Approved | DAVID STEPANYAN |
| Enclosure/Fence | 1/11/2022 | Corrections Issued | TROY SANDERS |
| Enclosure/Fence | 1/31/2022 | Corrections Issued | RYAN SALAZAR |
| Enclosure/Fence | 2/1/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Enclosure/Fence | 2/10/2022 | Approved | JEFFREY PARD |
| Pool Equipment Noise Test | 3/2/2022 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 3/8/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Not Ready | JOHN KIDWELL |
| Final | 4/22/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Final | 8/12/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Final | 8/22/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Approved | CHRIS CHRISTENSEN |