4181 N BAKMAN AVE 91602
Certificate Information: 4181 N BAKMAN AVE 91602
- Application / Permit
- 21047-20000-01977
- Plan Check / Job No.
- B21VN11823
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 30' SWIMMING POOL PER LACITY STANDARD PLAN 265
- Permit Issued
- Issued on 9/14/2021
- Issuing Office
- Current Status
- CofO Issued on 5/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2021 | OMAR GARNICA |
| Plan Check Approved | 9/13/2021 | OMAR GARNICA |
| Issued | 9/14/2021 | APPLICANT |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| CofO in Progress | 4/14/2022 | DAVID MATSON |
| Permit Finaled | 5/5/2022 | DANIEL ORRANTE |
| CofO Issued | 5/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Athlon Pool Company Inc; Lic. No.: 970093-C53 | 150 S GLENOAKS BLVD #9152 BURBANK, CA 91502 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 9/21/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 9/21/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Grounding or Bonding | 9/23/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 9/23/2021 | Corrections Issued | THOMAS FINNILA |
| Pool Piping | 9/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 9/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 9/29/2021 | Approved | THOMAS FINNILA |
| Deputy Shotcrete | 10/1/2021 | Conditional Approval | THOMAS FINNILA |
| Gas Piping or Gas Test | 12/27/2021 | Corrections Issued | THOMAS FINNILA |
| Rough-Electrical | 12/27/2021 | Partial Approval | THOMAS FINNILA |
| Gas Piping or Gas Test | 1/7/2022 | Partial Approval | THOMAS FINNILA |
| Rough-Electrical | 1/7/2022 | Partial Approval | THOMAS FINNILA |
| Deck | 1/27/2022 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 2/22/2022 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 2/25/2022 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 3/3/2022 | Corrections Issued | CALEB MEISTER |
| Enclosure/Fence | 3/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Approved | THOMAS FINNILA |
| Final | 3/16/2022 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Pool Equipment Noise Test | 3/21/2022 | Approved | FELIPE PENICHE |
| Final | 3/22/2022 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 3/30/2022 | Corrections Issued | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | DAVID MATSON |
| Final | 4/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/13/2022 | OK to Issue CofO | DAVID MATSON |