9710 N CREEMORE DR 91042

Certificate Information: 9710 N CREEMORE DR 91042

Application / Permit
21047-20000-01945
Plan Check / Job No.
B21VN11571
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 22' X 15' SWIMMING POOL WITH 6' X 6' ATTACHES SPA AS PER STANDARD PLAN # 265 - SEE COMMENTS
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 6/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 RARES BODEA
Corrections Issued 8/26/2021 RARES BODEA
Applicant returned to address corrections 9/1/2021 RARES BODEA
Applicant returned to address corrections 9/8/2021 RARES BODEA
Building Plans Picked Up 9/9/2021 APPLICANT
Plan Check Approved 11/3/2021 RARES BODEA
Issued 11/3/2021 APPLICANT
CofO in Progress 4/15/2022 MATTHEW NELSON
CofO Issued 6/13/2022 DANIEL ORRANTE
Permit Finaled 6/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 9/14/2021 DANG NGUYEN
ZI Cleared 9/14/2021 DANG NGUYEN
Miscellaneous Cleared 10/25/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/26/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/26/2021 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/3/2021 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 11/18/2021 Approved MATTHEW NELSON
Pool Piping 11/18/2021 Approved MATTHEW NELSON
Pre-Gunite 11/18/2021 Approved MATTHEW NELSON
Deck 1/11/2022 Approved MATTHEW NELSON
Grounding or Bonding 1/11/2022 Not Ready for Inspection MATTHEW NELSON
Pool/Spa Cover 1/11/2022 Not Ready for Inspection MATTHEW NELSON
Enclosure/Fence 3/21/2022 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV Not Ready MATTHEW NELSON
Enclosure/Fence 3/29/2022 Approved MATTHEW NELSON
Final 3/29/2022 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Not Ready MATTHEW NELSON
Final 4/15/2022 OK to Issue CofO MATTHEW NELSON
Final 4/15/2022 Partial Approval MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Approved MATTHEW NELSON