233 S LORRAINE BLVD 90004
Certificate Information: 233 S LORRAINE BLVD 90004
- Application / Permit
- 21047-20000-01926
- Plan Check / Job No.
- B21VN11454
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 43'-11" x 17'-2" POOL WITH 9'-0" x 8'-0" SPA AND AUTO POOL COVER PER CITY STD. PLAN #268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2021 | ALFRED RAMIREZ |
| Corrections Issued | 8/25/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/6/2022 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/12/2022 | ALFRED RAMIREZ |
| Issued | 1/20/2022 | APPLICANT |
| Building Plans Picked Up | 1/21/2022 | APPLICANT |
| CofO in Progress | 1/18/2023 | JEFFREY MEAD |
| CofO in Progress | 1/18/2023 | JEFFREY MEAD |
| CofO in Progress | 1/18/2023 | JEFFREY MEAD |
| Permit Finaled | 1/21/2023 | DEROLD HAUFF |
| CofO Issued | 1/21/2023 | DEROLD HAUFF |
| Permit Finaled | 1/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 9/13/2021 | NELSON RODRIGUEZ |
| ZI | Cleared | 9/13/2021 | NELSON RODRIGUEZ |
| Construction near power lines | Cleared | 12/15/2021 | RIDWAN HARDY |
Contact Information
| Contractor | L C Pools; Lic. No.: 538317-C53 | 3411 CLARENDON PL THOUSAND OAKS, CA 91360 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 3/11/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Gunite | 3/11/2022 | Approved | CHRIS CHRISTENSEN |
| Rough-Electrical | 3/11/2022 | Approved | CHRIS CHRISTENSEN |
| Rough-Plumbing | 3/11/2022 | Approved | CHRIS CHRISTENSEN |
| Deputy Shotcrete | 3/23/2022 | Corrections Issued | CRAIG DAVIS |
| Deck | 5/23/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Grounding or Bonding | 5/25/2022 | Approved | SHAVONNE ESPINOZA |
| Deck | 5/31/2022 | Approved | SHAVONNE ESPINOZA |
| Grounding or Bonding | 5/31/2022 | Approved | SHAVONNE ESPINOZA |
| Enclosure/Fence | 11/3/2022 | Partial Approval | JEFFREY MEAD |
| Enclosure/Fence | 12/1/2022 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 12/20/2022 | Approved | JEFFREY MEAD |
| Final | 12/20/2022 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/20/2022 | SGSOV Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 1/6/2023 | Approved | JEFFREY MEAD |
| Gas Piping or Gas Test | 1/6/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 1/6/2023 | Approved | JEFFREY MEAD |
| Final | 1/12/2023 | Partial Approval | JEFFREY MEAD |
| Final | 1/17/2023 | OK to Issue CofO | JEFFREY MEAD |