1416 N BELFAST DR 90069
Certificate Information: 1416 N BELFAST DR 90069
- Application / Permit
- 21047-20000-01917
- Plan Check / Job No.
- B21VN11389
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 13'0"36'0"POOL AND 7'0"X8'0" SPA PER STANDARD PLAN#268 & DETAIL #630
- Permit Issued
- Issued on 3/1/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | MARVEL DELACRUZ |
| Corrections Issued | 9/18/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 9/24/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/28/2021 | APPLICANT |
| Applicant returned to address corrections | 1/26/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 1/26/2022 | MARVEL DELACRUZ |
| No Progress | 1/26/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 1/27/2022 | MARVEL DELACRUZ |
| Issued | 3/1/2023 | APPLICANT |
| CofO in Progress | 4/23/2024 | BRIAN SULLIVAN |
| Permit Finaled | 4/23/2024 | RONALD MYRICK |
| Permit Finaled | 4/23/2024 | RONALD MYRICK |
| CofO Issued | 4/23/2024 | RONALD MYRICK |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Designer Custom Pools Inc; Lic. No.: 1086707-C53 | 3749 E COLORADO BLVD PASADENA, CA 91107 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Meehan,, Michelle Marie; Lic. No.: C57460 | 5435 LEWIS RD AGOURA HILLS, CA 91301 |
| Geologist | Cugno,, Giuseppe; Lic. No.: EG1804 | 1461 E CHEVY CHASE DR 200 BYER GEOTECHNICAL, INC. GLENDALE, CA 91206 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 4/3/2023 | Partial Approval | STUART CHAPMAN |
| Pre-Gunite | 4/3/2023 | Approved | STUART CHAPMAN |
| Rough-Electrical | 4/3/2023 | Partial Approval | STUART CHAPMAN |
| Rough-Plumbing | 4/3/2023 | Approved | STUART CHAPMAN |
| Deputy Shotcrete | 4/17/2023 | Conditional Approval | RUBEN SALAS |
| Grounding or Bonding | 7/6/2023 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 9/25/2023 | Partial Inspection | STUART CHAPMAN |
| Enclosure/Fence | 10/27/2023 | Approved | STUART CHAPMAN |
| Pool Equipment Noise Test | 11/7/2023 | Approved | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 11/16/2023 | Approved | STUART CHAPMAN |
| Final | 11/16/2023 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | STUART CHAPMAN |
| Final | 11/17/2023 | Corrections Issued | STUART CHAPMAN |
| Final | 4/23/2024 | OK to Issue CofO | BRIAN SULLIVAN |