321 N ALMA REAL DR 90272
Certificate Information: 321 N ALMA REAL DR 90272
- Application / Permit
- 21047-20000-01916
- Plan Check / Job No.
- B21VN11385
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL (E) POOL TO REPLASTER AND RETILE AND ADD NEW 6' X 8' SPA INSIDE EXISTING POOL SHELL PER STANDARD PLAN #270. RELOCATE POOL EQUIPMENT.
- Permit Issued
- Issued on 12/12/2021
- Issuing Office
- Current Status
- CofO Issued on 10/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/27/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/14/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| Issued | 12/12/2021 | APPLICANT |
| CofO in Progress | 9/26/2024 | EVAN COOPER |
| CofO Issued | 10/30/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/30/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZI | Cleared | 9/10/2021 | LAUREN PADICK |
| Coastal Zone | Cleared | 10/27/2021 | NOAH MCCOY |
Contact Information
| Contractor | Marino Pool And Spa; Lic. No.: 528696-C53 | 5739 KANAN RD #364 AGOURA HILLS, CA 91301 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/26/2022 | Approved | ANDREW NAVE |
| Grounding or Bonding | 1/26/2022 | Corrections Issued | ANDREW NAVE |
| Pool Piping | 1/26/2022 | Corrections Issued | ANDREW NAVE |
| Deputy Shotcrete | 1/27/2022 | Conditional Approval | ANDREW NAVE |
| Grounding or Bonding | 1/27/2022 | Partial Approval | ANDREW NAVE |
| Pool Piping | 1/27/2022 | Approved | ANDREW NAVE |
| Final | 7/11/2024 | Not Ready for Inspection | EVAN COOPER |
| Pre-Gunite | 7/11/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Approved | EVAN COOPER |
| Enclosure/Fence | 7/23/2024 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 7/30/2024 | Not Ready for Inspection | EVAN COOPER |
| Final | 7/30/2024 | Not Ready for Inspection | EVAN COOPER |
| Enclosure/Fence | 8/1/2024 | Approved | EVAN COOPER |
| Final | 9/17/2024 | Corrections Issued | EVAN COOPER |
| Pool Equipment Noise Test | 9/19/2024 | Approved | EUSEBIO GUZMAN |
| Final | 9/25/2024 | OK to Issue CofO | EVAN COOPER |