11215 N RINCON AVE 91340

Certificate Information: 11215 N RINCON AVE 91340

Application / Permit
21047-20000-01898
Plan Check / Job No.
B21VN11279
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) 17' - 6" X 28' IRREGULAR SHAPED SWIMMING POOL PER LACITY STANDARD PLAN 268 AND SUPPLEMENTAL DETAIL 271-60
Permit Issued
Issued on 2/25/2022
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 OMAR GARNICA
Corrections Issued 10/28/2021 OMAR GARNICA
Applicant returned to address corrections 1/3/2022 OMAR GARNICA
Plan Check Approved 2/23/2022 OMAR GARNICA
Issued 2/25/2022 APPLICANT
Building Plans Picked Up 2/28/2022 APPLICANT
CofO in Progress 2/12/2024 JENNIFER RABUCHIN
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Blue Haven Pools; Lic. No.: 816057-B 780 S MILLIKEN AVE STE G      ONTARIO, CA 91761
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 5/9/2022 No Access for Inspection JENNIFER RABUCHIN
Pre-Gunite 5/11/2022 No Access for Inspection RAUL OLAGI
Pre-Gunite 5/17/2022 Approved JENNIFER RABUCHIN
Deputy Shotcrete 6/16/2022 Partial Approval JENNIFER RABUCHIN
Deck 12/14/2022 Corrections Issued ARAM AVEDISIAN
Deck 1/18/2023 Approved MICHEL ABAJAN
Enclosure/Fence 6/8/2023 Corrections Issued ROBERT GOLD
Enclosure/Fence 9/20/2023 Approved JENNIFER RABUCHIN
Equipment Noise Level 10/11/2023 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 10/13/2023 Approved JENNIFER RABUCHIN
Final 10/13/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Approved JENNIFER RABUCHIN
Special/Order Compliance 10/13/2023 Corrections Issued JENNIFER RABUCHIN
Final 2/13/2024 OK to Issue CofO JENNIFER RABUCHIN