13687 N LINFIELD AVE 91342
Certificate Information: 13687 N LINFIELD AVE 91342
- Application / Permit
- 21047-20000-01868
- Plan Check / Job No.
- B21VN11053
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 26' POOL WITH A 7' X 7' SPA AND 7' X 7' BAJA ALL WORK PER STD PLAN #268
- Permit Issued
- Issued on 10/4/2021
- Issuing Office
- Current Status
- CofO Issued on 7/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/19/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 8/31/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 9/14/2021 | PETER MOSESIAN |
| Applicant returned to address corrections | 9/14/2021 | PETER MOSESIAN |
| Applicant returned to address corrections | 10/1/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 10/4/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/4/2021 | APPLICANT |
| CofO in Progress | 7/13/2022 | ARAM AVEDISIAN |
| Permit Finaled | 7/16/2022 | MICHAEL SMITH |
| CofO Issued | 7/16/2022 | MICHAEL SMITH |
| Permit Finaled | 7/16/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/3/2021 | PABLO ESTRADA |
| Construction near power lines | Cleared | 9/23/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 10/4/2021 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Plascencia Pools & Landscaping; Lic. No.: 790546-C53 | 13803 LOUVRE STREET PACOIMA, CA 91331 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/18/2021 | Approved | JOHN HAYES |
| Deck | 1/10/2022 | Corrections Issued | JOHN HAYES |
| Deck | 1/12/2022 | Approved | JOHN HAYES |
| Enclosure/Fence | 3/9/2022 | Approved | MICHEL ABAJAN |
| Pool Equipment Noise Test | 4/4/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 6/6/2022 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/13/2022 | Approved | ARAM AVEDISIAN |
| Final | 7/13/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Approved | ARAM AVEDISIAN |