2132 S GLYNDON AVE 90291

Certificate Information: 2132 S GLYNDON AVE 90291

Application / Permit
21047-20000-01817
Plan Check / Job No.
B21VN10700
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 10' X 16' POOL PER LA CITY STANDARD PLAN #268
Permit Issued
Issued on 8/30/2021
Issuing Office
Current Status
CofO Issued on 3/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2021 APPLICANT
Assigned to Plan Check Engineer 8/11/2021 JENNIFER LEE
Corrections Issued 8/11/2021 JENNIFER LEE
Plan Check Approved 8/26/2021 JENNIFER LEE
Issued 8/30/2021 APPLICANT
Building Plans Picked Up 9/3/2021 APPLICANT
CofO in Progress 3/9/2022 DAVID FEILER
Permit Finaled 3/17/2022 DANIEL ORRANTE
CofO Issued 3/17/2022 DANIEL ORRANTE
Permit Finaled 3/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 2646 DUPONT DR STE 60 #348      IRVINE, CA 92612
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 12/6/2021 Corrections Issued DAVID FEILER
Pre-Gunite 12/10/2021 Approved ENRIQUE MIRELES
Deck 1/10/2022 No Access for Inspection JOHN KAYON
Grounding or Bonding 1/12/2022 No Access for Inspection JOHN KAYON
Deck 2/8/2022 Approved RYAN SALAZAR
Enclosure/Fence 2/8/2022 Corrections Issued RYAN SALAZAR
Grounding or Bonding 2/8/2022 Approved RYAN SALAZAR
Enclosure/Fence 2/10/2022 Corrections Issued DAVID FEILER
Enclosure/Fence 2/14/2022 Approved DAVID FEILER
Excavation/Setback/Form/Re-Bar 2/28/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Not Ready DAVID FEILER
Pool Equipment Noise Test 3/1/2022 Approved JAMES VORHIS
Final 3/2/2022 Corrections Issued DAVID FEILER
Final 3/8/2022 OK to Issue CofO DAVID FEILER
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Approved DAVID FEILER