4634 N KRAFT AVE 91602
Certificate Information: 4634 N KRAFT AVE 91602
- Application / Permit
- 21047-20000-01782
- Plan Check / Job No.
- B21VN10491
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW(28'-3"x17'-0") POOL AND 10'-0" DIAMETER SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 9/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2021 | PETER MOSESIAN |
| Corrections Issued | 8/9/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| Plan Check Approved | 10/27/2021 | PETER MOSESIAN |
| Issued | 11/4/2021 | APPLICANT |
| CofO in Progress | 9/16/2022 | ALAN MORELOS |
| CofO Issued | 9/22/2022 | MICHAEL SMITH |
| Permit Finaled | 9/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Aldan Construction & Remodeling Inc; Lic. No.: 1030243-B | 8549 WILSHIRE BLVD #1458 BEVERLY HILLS, CA 90211 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 4/11/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 4/11/2022 | Corrections Issued | THOMAS FINNILA |
| Rough-Electrical | 4/11/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/19/2022 | Approved | THOMAS FINNILA |
| Gas Piping or Gas Test | 4/19/2022 | Partial Approval | THOMAS FINNILA |
| Grounding or Bonding | 4/19/2022 | Partial Approval | THOMAS FINNILA |
| Pre-Inspection | 7/26/2022 | Partial Inspection | CALEB MEISTER |
| Enclosure/Fence | 8/9/2022 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 8/15/2022 | Approved | GREGG CUMMINGS |
| Final | 9/13/2022 | Corrections Issued | ALAN MORELOS |
| Pre-Gunite | 9/13/2022 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | ALAN MORELOS |
| Final | 9/16/2022 | OK to Issue CofO | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | ALAN MORELOS |