3977 S DEGNAN BLVD 90008
Certificate Information: 3977 S DEGNAN BLVD 90008
- Application / Permit
- 21047-20000-01729
- Plan Check / Job No.
- B21VN10057
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 7''-0" x 10'-0" SPA PER LA CITY STANDARD PLAN#268 AND ENGINEERING DETAIL #220-60.
- Permit Issued
- Issued on 9/3/2021
- Issuing Office
- Current Status
- CofO Issued on 8/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2021 | SERGIO MUNIZ |
| Corrections Issued | 8/2/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 8/5/2021 | APPLICANT |
| Plan Check Approved | 8/18/2021 | SARKIS HARABEDIAN |
| Issued | 9/3/2021 | APPLICANT |
| CofO in Progress | 7/15/2022 | ANTHONY EGSON |
| CofO in Progress | 7/15/2022 | ANTHONY EGSON |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| CofO Issued | 8/13/2022 | DEROLD HAUFF |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Ahern Construction Corporation; Lic. No.: 687780-B | 3835-R THOUSAND OAKS BLVD #118 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Partial Inspection | ADAM ESCOTO |
| Pre-Gunite | 10/7/2021 | Corrections Issued | DAVID FEILER |
| Pre-Gunite | 10/7/2021 | Partial Inspection | ADAM ESCOTO |
| Special/Order Compliance | 10/7/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 10/12/2021 | Approved | ADAM ESCOTO |
| Pre-Gunite | 10/12/2021 | Approved | ADAM ESCOTO |
| Grounding or Bonding | 2/7/2022 | Approved | JOAQUIN GREENOUGH |
| Enclosure/Fence | 3/22/2022 | Approved | ANTHONY EGSON |
| Equipment Noise Level | 5/19/2022 | Approved | JAMES VORHIS |
| Final | 5/23/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 6/29/2022 | OK to Issue CofO | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Approved | ANTHONY EGSON |