12075 W MOUND VIEW PL 91604
Certificate Information: 12075 W MOUND VIEW PL 91604
- Application / Permit
- 21047-20000-01699
- Plan Check / Job No.
- B21VN09781
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12'x 25'-5" POOL W/ 6'x12' SPA ON PILES; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 7/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | SEAN SHAHMIRI |
| Corrections Issued | 8/14/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 8/17/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 12/1/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 1/4/2022 | SEAN SHAHMIRI |
| Issued | 1/6/2022 | APPLICANT |
| CofO in Progress | 5/12/2022 | ARAM AVEDISIAN |
| Permit Finaled | 7/6/2022 | MICHAEL SMITH |
| CofO Issued | 7/6/2022 | MICHAEL SMITH |
| Permit Finaled | 7/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/13/2021 | SEAN SHAHMIRI |
| Construction within easement | Cleared | 8/16/2021 | JOHN BACON |
Contact Information
| Contractor | Amazon Pools; Lic. No.: 830886-C53 | 18653 VENTURA BLVD #139 TARZANA, CA 91356 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 1/24/2022 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 2/14/2022 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 2/14/2022 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 2/14/2022 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 2/15/2022 | Conditional Approval | ARAM AVEDISIAN |
| Gas Piping or Gas Test | 3/22/2022 | Corrections Issued | ARAM AVEDISIAN |
| Gas Piping or Gas Test | 3/30/2022 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 4/4/2022 | Corrections Issued | ARAM AVEDISIAN |
| Enclosure/Fence | 4/5/2022 | Approved | ARAM AVEDISIAN |
| Equipment Noise Level | 4/13/2022 | Approved | FELIPE PENICHE |
| Final | 5/5/2022 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2022 | SGSOV Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 5/12/2022 | Approved | ARAM AVEDISIAN |
| Final | 5/12/2022 | OK to Issue CofO | ARAM AVEDISIAN |