20663 W CLARK ST 91367

Certificate Information: 20663 W CLARK ST 91367

Application / Permit
21047-20000-01659
Plan Check / Job No.
B21VN09488
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 31'-6" X 13' IRREGULAR SHAPE POOL WITH 7'-0" X 9'6" SPA PER ENGINEER.
Permit Issued
Issued on 10/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 JESSE ARELLANO
Corrections Issued 7/29/2021 JESSE ARELLANO
Applicant returned to address corrections 8/23/2021 JENNIFER LEE
Applicant returned to address corrections 9/7/2021 JESSE ARELLANO
Applicant returned to address corrections 10/6/2021 JESSE ARELLANO
Applicant returned to address corrections 10/27/2021 JESSE ARELLANO
Building Plans Picked Up 10/29/2021 APPLICANT
Plan Check Approved 10/17/2022 PINANK PATEL
Issued 10/17/2022 APPLICANT
CofO in Progress 1/29/2025 ALEXANDER HANDY
Permit Finaled 2/6/2025 JOHN JANSON
CofO Issued 2/6/2025 JOHN JANSON
Permit Finaled 2/6/2025 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/23/2021 JENNIFER LEE
Construction near power lines Cleared 8/27/2021 WALTER RAMIREZ
Construction within easement Cleared 8/27/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 11/16/2022 Not Ready for Inspection STEVEN BACK
Pool Piping 11/16/2022 Not Ready for Inspection STEVEN BACK
Pre-Gunite 11/16/2022 Corrections Issued STEVEN BACK
Rough-Electrical 11/16/2022 Approved STEVEN BACK
Rough-Plumbing 11/16/2022 Not Ready for Inspection STEVEN BACK
Special/Order Compliance 11/16/2022 Partial Inspection KRISTEN CAUSEY
Pre-Gunite 11/23/2022 Approved STEVEN BACK
Deck 12/22/2022 Approved VINCENT HANLEY
Grounding or Bonding 12/22/2022 Approved VINCENT HANLEY
Enclosure/Fence 1/20/2023 Corrections Issued ALEXANDER HANDY
Grounding or Bonding 1/20/2023 Approved ALEXANDER HANDY
Rough-Plumbing 1/20/2023 Approved ALEXANDER HANDY
Enclosure/Fence 1/24/2023 Corrections Issued ALEXANDER HANDY
Enclosure/Fence 1/27/2023 Approved ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 2/10/2023 Not Ready for Inspection ALEXANDER HANDY
Final 2/10/2023 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/10/2023 SGSOV Not Ready ALEXANDER HANDY
Equipment Noise Level 2/14/2023 Approved ALFREDO FLORES
Pool Equipment Noise Test 2/14/2023 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 2/16/2023 Approved ALEXANDER HANDY
Final 2/16/2023 Conditional Approval ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/16/2023 SGSOV Approved ALEXANDER HANDY
Final 1/30/2025 OK to Issue CofO ALEXANDER HANDY
Enclosure/Fence 2/6/2025 Approved ALEXANDER HANDY
Enclosure/Fence 2/7/2025 Not Ready for Inspection ALEXANDER HANDY