20663 W CLARK ST 91367
Certificate Information: 20663 W CLARK ST 91367
- Application / Permit
- 21047-20000-01659
- Plan Check / Job No.
- B21VN09488
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 31'-6" X 13' IRREGULAR SHAPE POOL WITH 7'-0" X 9'6" SPA PER ENGINEER.
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | JESSE ARELLANO |
| Corrections Issued | 7/29/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 8/23/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 9/7/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/6/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/27/2021 | JESSE ARELLANO |
| Building Plans Picked Up | 10/29/2021 | APPLICANT |
| Plan Check Approved | 10/17/2022 | PINANK PATEL |
| Issued | 10/17/2022 | APPLICANT |
| CofO in Progress | 1/29/2025 | ALEXANDER HANDY |
| Permit Finaled | 2/6/2025 | JOHN JANSON |
| CofO Issued | 2/6/2025 | JOHN JANSON |
| Permit Finaled | 2/6/2025 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/23/2021 | JENNIFER LEE |
| Construction near power lines | Cleared | 8/27/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 8/27/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 11/16/2022 | Not Ready for Inspection | STEVEN BACK |
| Pool Piping | 11/16/2022 | Not Ready for Inspection | STEVEN BACK |
| Pre-Gunite | 11/16/2022 | Corrections Issued | STEVEN BACK |
| Rough-Electrical | 11/16/2022 | Approved | STEVEN BACK |
| Rough-Plumbing | 11/16/2022 | Not Ready for Inspection | STEVEN BACK |
| Special/Order Compliance | 11/16/2022 | Partial Inspection | KRISTEN CAUSEY |
| Pre-Gunite | 11/23/2022 | Approved | STEVEN BACK |
| Deck | 12/22/2022 | Approved | VINCENT HANLEY |
| Grounding or Bonding | 12/22/2022 | Approved | VINCENT HANLEY |
| Enclosure/Fence | 1/20/2023 | Corrections Issued | ALEXANDER HANDY |
| Grounding or Bonding | 1/20/2023 | Approved | ALEXANDER HANDY |
| Rough-Plumbing | 1/20/2023 | Approved | ALEXANDER HANDY |
| Enclosure/Fence | 1/24/2023 | Corrections Issued | ALEXANDER HANDY |
| Enclosure/Fence | 1/27/2023 | Approved | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 2/10/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 2/10/2023 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Not Ready | ALEXANDER HANDY |
| Equipment Noise Level | 2/14/2023 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 2/14/2023 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Approved | ALEXANDER HANDY |
| Final | 2/16/2023 | Conditional Approval | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | ALEXANDER HANDY |
| Final | 1/30/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Enclosure/Fence | 2/6/2025 | Approved | ALEXANDER HANDY |
| Enclosure/Fence | 2/7/2025 | Not Ready for Inspection | ALEXANDER HANDY |