4449 N NOGALES DR 91356
Certificate Information: 4449 N NOGALES DR 91356
- Application / Permit
- 21047-20000-01653
- Plan Check / Job No.
- B21VN09444
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL (E) POOL AND ADD 8' DIAMETER SPA PER STANDARD PLAN #268 AND ENGINEERING DETAILS. RELOCATE POOL EQUIPMENT.
- Permit Issued
- Issued on 9/1/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/29/2021 | RAPHAEL ROSAS |
| Issued | 9/1/2021 | APPLICANT |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| CofO in Progress | 8/11/2022 | DAVID SANDOVAL |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| ZA Case | Cleared | 8/20/2021 | MIGUEL GAMBOA |
| Grading Pre-Inspection | Cleared | 8/30/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-C53 | 2646 DUPONT DR STE 60 #348 IRVINE, CA 92612 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/3/2021 | Conditional Approval | DAVID SANDOVAL |
| Pre-Gunite | 11/5/2021 | Corrections Issued | DAVID SANDOVAL |
| Deputy Shotcrete | 11/15/2021 | Approved | DAVID SANDOVAL |
| Deck | 2/8/2022 | Corrections Issued | DAVID SANDOVAL |
| Grounding or Bonding | 2/8/2022 | Partial Approval | DAVID SANDOVAL |
| Deck | 2/24/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Enclosure/Fence | 3/9/2022 | Corrections Issued | DAVID SANDOVAL |
| Enclosure/Fence | 4/6/2022 | Corrections Issued | DAVID SANDOVAL |
| Enclosure/Fence | 6/1/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Enclosure/Fence | 6/6/2022 | Approved | PETER FOLLING |
| Equipment Noise Level | 7/11/2022 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 7/11/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 7/20/2022 | Approved | VINCENT HANLEY |
| Final | 7/20/2022 | Corrections Issued | VINCENT HANLEY |
| Pre-Gunite | 7/20/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/20/2022 | SGSOV Approved | VINCENT HANLEY |
| Final | 8/11/2022 | OK to Issue CofO | DAVID SANDOVAL |