9687 N SANDUSKY AVE 91331
Certificate Information: 9687 N SANDUSKY AVE 91331
- Application / Permit
- 21047-20000-01642
- Plan Check / Job No.
- B21VN09370
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15'-8" X 17'-8" SWIMMING POOL AND 6' X 6' SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAILS
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 12/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2021 | SERGIO MUNIZ |
| Corrections Issued | 7/19/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 8/27/2021 | PINANK PATEL |
| Applicant returned to address corrections | 11/24/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 11/30/2021 | SERGIO MUNIZ |
| Plan Check Approved | 11/30/2021 | JEROME MAGAT PALMA |
| Issued | 1/11/2022 | APPLICANT |
| Building Plans Picked Up | 1/12/2022 | APPLICANT |
| CofO in Progress | 12/19/2022 | MICHEL ABAJAN |
| CofO Issued | 12/20/2022 | MICHAEL SMITH |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/30/2021 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/1/2022 | Partial Approval | MICHEL ABAJAN |
| Gas Piping or Gas Test | 4/1/2022 | Partial Approval | MICHEL ABAJAN |
| Grounding or Bonding | 4/1/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 4/1/2022 | Partial Inspection | MICHEL ABAJAN |
| Pool Piping | 4/1/2022 | Partial Inspection | MICHEL ABAJAN |
| Pre-Gunite | 4/1/2022 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/13/2022 | Approved | MICHEL ABAJAN |
| Grounding or Bonding | 4/13/2022 | Approved | MICHEL ABAJAN |
| Pool Piping | 4/13/2022 | Approved | MICHEL ABAJAN |
| Pre-Gunite | 4/13/2022 | Approved | MICHEL ABAJAN |
| Rough-Electrical | 4/13/2022 | Partial Approval | MICHEL ABAJAN |
| Rough-Plumbing | 4/13/2022 | Partial Approval | MICHEL ABAJAN |
| Enclosure/Fence | 6/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Enclosure/Fence | 7/22/2022 | Approved | MICHEL ABAJAN |
| Pool Equipment Noise Test | 12/14/2022 | Approved | FELIPE PENICHE |
| Final | 12/16/2022 | OK to Issue CofO | MICHEL ABAJAN |