7711 S DALTON AVE 90047

Certificate Information: 7711 S DALTON AVE 90047

Application / Permit
21047-20000-01600
Plan Check / Job No.
B21VN09020
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 11'-0" X 24'-0" POOL WITH 8' X 4.5' SPA PER LA CITY STANDARD PLAN #268 AND SUPPLEMENTAL DETAIL #271-60, 672
Permit Issued
Issued on 11/15/2021
Issuing Office
Current Status
Issued on 11/15/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/13/2021 JESSE ARELLANO
Corrections Issued 7/13/2021 JESSE ARELLANO
Applicant returned to address corrections 9/28/2021 JESSE ARELLANO
Issued 11/15/2021 APPLICANT
Building Plans Picked Up 11/16/2021 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 9/20/2021 RIDWAN HARDY

Contact Information

Contractor Avcore Inc; Lic. No.: 1059954-C53 2001 S ELECTRIC AVENUE      ALHAMBRA, CA 91803
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 12/20/2021 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 12/20/2021 Partial Inspection ADAM ESCOTO
Final 12/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Piping or Gas Test 12/27/2021 Partial Approval ALEJANDRO DE ARTOLA
Grounding or Bonding 12/27/2021 Approved ALEJANDRO DE ARTOLA
Pre-Gunite 12/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
Rough-Electrical 12/27/2021 Approved ALEJANDRO DE ARTOLA
Rough-Plumbing 12/27/2021 Approved ALEJANDRO DE ARTOLA
Deputy Shotcrete 12/30/2021 Conditional Approval ALEJANDRO DE ARTOLA
Deck 2/17/2022 Approved LILIANA PORTILLO
Enclosure/Fence 3/11/2022 Corrections Issued ALEJANDRO DE ARTOLA
Enclosure/Fence 3/30/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 4/28/2022 Approved LILIANA PORTILLO
Final 4/28/2022 Partial Approval LILIANA PORTILLO
Pre-Gunite 4/28/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/28/2022 SGSOV Approved LILIANA PORTILLO
Special/Order Compliance 4/28/2022 Approved HORACE FULTZ
Equipment Noise Level 5/3/2022 Approved JAMES VORHIS