6124 W 76TH ST 90045

Certificate Information: 6124 W 76TH ST 90045

Application / Permit
21047-20000-01589
Plan Check / Job No.
B21VN08932
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16' X 32' POOL AND 6' X 6' SPA PER STD PLA #268.
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/12/2021 PINANK PATEL
Corrections Issued 7/12/2021 PINANK PATEL
Plan Check Approved 8/27/2021 PINANK PATEL
Issued 9/1/2021 APPLICANT
Building Plans Picked Up 9/9/2021 APPLICANT
CofO in Progress 3/14/2023 BOBBY KEY
Permit Finaled 3/15/2023 DANIEL ORRANTE
CofO Issued 3/15/2023 DANIEL ORRANTE
Permit Finaled 3/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 8/19/2021 WALTER RAMIREZ
Construction within easement Cleared 8/19/2021 WALTER RAMIREZ

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 2646 DUPONT DR STE 60 #348      IRVINE, CA 92612
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/10/2022 Approved BOBBY KEY
Grounding or Bonding 1/10/2022 Approved BOBBY KEY
Pool Piping 1/10/2022 Approved BOBBY KEY
Pre-Gunite 1/10/2022 Approved BOBBY KEY
Deputy Shotcrete 1/14/2022 Conditional Approval BOBBY KEY
Deck 4/1/2022 Approved BOBBY KEY
Grounding or Bonding 4/1/2022 Approved BOBBY KEY
Enclosure/Fence 4/19/2022 Approved JESUS RODRIGUEZ
Pool Equipment Noise Test 4/27/2022 Approved AGUSTIN ALVAREZMORALES
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Not Ready DAVID FEILER
Final 12/19/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Not Ready HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Not Ready BOBBY KEY
ELECTRICAL-Final 3/14/2023 Approved BOBBY KEY
Final 3/14/2023 OK to Issue CofO BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Approved BOBBY KEY