4213 N HAZELTINE AVE 91423
Certificate Information: 4213 N HAZELTINE AVE 91423
- Application / Permit
- 21047-20000-01587
- Plan Check / Job No.
- B21VN08900
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30' X 15' SWIMMING POOL WITH 7' X 7' SPA PER LA CITY STANDARD PLAN #270.
- Permit Issued
- Issued on 10/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 7/12/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 9/28/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 10/4/2021 | APPLICANT |
| Issued | 10/7/2021 | APPLICANT |
| CofO in Progress | 4/13/2022 | MISAEL ESPARZA |
| CofO Issued | 6/11/2022 | MICHAEL SMITH |
| Permit Finaled | 6/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/22/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/22/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 9/28/2021 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Raub Doug Design & Development Inc; Lic. No.: 723625-B | 14066 ROBLAR ROAD SHERMAN OAKS, CA 91423 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/12/2021 | Approved | MISAEL ESPARZA |
| Deputy Shotcrete | 11/15/2021 | Approved | MISAEL ESPARZA |
| Rough-Plumbing | 11/15/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Grounding or Bonding | 12/1/2021 | Approved | MISAEL ESPARZA |
| Gas Piping or Gas Test | 12/3/2021 | Corrections Issued | MISAEL ESPARZA |
| Gas Piping or Gas Test | 12/8/2021 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 2/22/2022 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 3/1/2022 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Approved | MISAEL ESPARZA |
| Final | 3/17/2022 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Pool Equipment Noise Test | 3/22/2022 | Approved | ALFREDO FLORES |
| ELECTRICAL-Final | 3/29/2022 | Approved | MISAEL ESPARZA |
| Final | 3/29/2022 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Final | 4/12/2022 | OK to Issue CofO | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Approved | MISAEL ESPARZA |