5817 N MCDONIE AVE 91367
Certificate Information: 5817 N MCDONIE AVE 91367
- Application / Permit
- 21047-20000-01568
- Plan Check / Job No.
- B21VN08727
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17' x 32' POOL.
- Permit Issued
- Issued on 7/26/2021
- Issuing Office
- Current Status
- CofO Issued on 3/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | LUIS RINCON |
| Corrections Issued | 7/9/2021 | LUIS RINCON |
| Plan Check Approved | 7/26/2021 | LUIS RINCON |
| Issued | 7/26/2021 | APPLICANT |
| Building Plans Picked Up | 8/3/2021 | APPLICANT |
| CofO in Progress | 3/4/2022 | STEVEN BACK |
| CofO Issued | 3/10/2022 | JOHN JANSON |
| Permit Finaled | 3/10/2022 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/26/2021 | LUIS RINCON |
Contact Information
| Contractor | C I D Builders And Developers Inc; Lic. No.: 958193-B | 4804 LAUREL CYN BLVD #755 STUDIO CITY, CA 91607 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/19/2021 | Corrections Issued | HENRY KIM |
| Gas Piping or Gas Test | 8/26/2021 | Approved | HENRY KIM |
| Grounding or Bonding | 8/26/2021 | Partial Approval | HENRY KIM |
| Pool Piping | 8/26/2021 | Approved | HENRY KIM |
| Pre-Gunite | 8/26/2021 | Approved | HENRY KIM |
| Rough-Electrical | 8/26/2021 | Approved | HENRY KIM |
| Deck | 10/4/2021 | Approved | STEVEN BACK |
| Enclosure/Fence | 11/17/2021 | Corrections Issued | STEVEN BACK |
| Enclosure/Fence | 1/24/2022 | Not Ready for Inspection | STEVEN BACK |
| Enclosure/Fence | 2/16/2022 | Approved | STEVEN BACK |
| Equipment Noise Level | 2/23/2022 | Approved | ALFREDO FLORES |
| Deck | 2/25/2022 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Approved | STEVEN BACK |
| Final | 2/25/2022 | Corrections Issued | STEVEN BACK |
| Rough-Electrical | 2/25/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | STEVEN BACK |
| Deck | 3/4/2022 | Approved | STEVEN BACK |
| Final | 3/4/2022 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/4/2022 | SGSOV Approved | STEVEN BACK |